Security Fire Systems-170530 Big D Concrete, Inc 10361 Bickham Rd. Dallas, TX 75220 Plant (972) 401-2443 Fax (972) 506-8270 Dispatch: (817) 532-7486/(214) 912-8038 MAY 30, 2017 To: MOSS UTILITIES Project: SECURITY FIRE SYSTEM - #1720, CITY OF COPPELL RE: Submittal Documents Please find enclosed our submittal documents for the above referenced project. Big D will guarantee strength according to ASTM C94 only if field sampling has been accomplished per ASTM C172 and ASTM C31 and the laboratory testing also fully complies with ASTM C39 and ASTM C1077. Big D Concrete will not guarantee strength for the mix designs submitted if the following conditions occur : 1.) the concrete temperature is below 55 degrees or above 95 degrees, 2.) the design plastic properties – “slump” is exceeded by additional water added on site, 3.) the concrete is not placed within 90 minutes of the batch time. It is the purchaser’s responsibility to inform Big D Concrete of any planned or unplanned delays during the pouring process so deliveries can be coordinated. The concrete temperature requirements stated above shall not supersede any more restrictive temperatures specifications. For concrete ordered during hot weather, Big D Concrete will require the purchaser to order ice to meet concrete temperature specifications. All concrete shall be placed and cured according to the appropriate ASTM guidelines and recommendations for hot and cold weather concreting. Test cylinders must be cured per ACI 301, section 1.6.3.2.d for Big D Concrete to guarantee strength. It will be the purchaser’s responsibility for precautions to protect the placed concrete from excessive heat, wind, rain, hail, and low humidity per ACI 305 guidelines. Big D Concrete will not take responsibility for concrete defects relating to the finishing process, (cracking, scaling, dusting, delamination, discoloration, etc. This also includes proper preparation, compaction, and wetting of the subgrade or forms - especially during hot weather, as well as the proper placement of rebar and control joints. During periods of cold weather, it is the purchaser’s responsibility to protect the concrete from freezing during the initial curing period – the first 7 days. Big D Concrete will not be responsible for any concrete rejected for non-compliance of concrete temperatures for not ordering or declining temperature control measures – hot water in cold temperatures or ice during excessive heat. Big D Concrete emphasizes the need to avoid free fall of concrete which result in the loss of air. For pumped concrete with different boom configurations, hose extensions, line reductions, and free fall distances which are all out of Big D Concrete’s control, Big D Concrete will not be responsible for any loss of air content or costs associated with either rejected fresh concrete or the removal and replacement of hardened concrete due to the non-compliance of required air content or placing concrete outside of the specified slump range or exceeding the time limitations of concrete placement. Per ASTM standards, Big D is requesting the testing lab use 6 x 12 cylinders due to the 1” aggregate. Thank you for the opportunity to submit these documents. We are requesting a copy of the approved submittal. Please order by our designated mix. We are also requesting Big D Concrete be added to the list of names receiving copies of testing laboratory information for this project. Regards, David Wittwer Quality Control Manager Big D Concrete, Inc. Concrete Mix Design (Absolute Volume Method Designed for One Cubic Yard) DATE:5/31/17 w/c 0.52 Designed By:David Wittwer Big D Order Mix # SIDEWALKS Class Concrete 3,000 PSI IN 28 DAYS Project:SECURITY FIRE SYSTEM, CITY OF COPPELL MOSS UTILITIES - #1720 W/C: Max 0.52 Design 0.52 Description:5.0 SACK, WR, AE, FA, Slump - 4" +/- 1" S.G. Min. Spec. CF 470 Design 376 Agg. No. 1 2.670 % of mix 42.0%Concrete Sand Fly Ash: 20%Design 94 Agg. No. 2 % of mix 0.0%3/8" Pea Gravel Designed for:4.5 % Air + / - 1.5%Agg. No. 3 2.677 % of mix 58.0%#57 Limestone CLASS A - 1" Admix:100% RETARDER - SYAD 75 Saturated Surface Dry Weights Per Cubic Yard Material Source Quantity Vol.(cf) Cement =Holcim Type I/II Midlothian 376 lbs.1.913 Fly Ash =Headwaters Type "C" 94 lbs.0.558 Air =4.5 %1.215 Water = City of Dallas 244 lbs 3.917 29.3 (gal) Agg. No. 1 - Sand Patriot Materials, Chatfield, Tx 1359 lbs.8.147 Agg. No. 2 - Pea Gravel 0 lbs.0.000 Agg. No. 3 - 1" - #57 Limestone VULCAN - Weatherford 1877 lbs.11.251 Volume for One Cubic Yard =3950.00 27.00 Weight per Cu. Ft. Fresh Conc. - Design 146.34 AEA:1.5 OZ/CY Weight per Cu. Ft. Fresh Conc. - Air Free 153.24 Water Reducer:23.5 OZ/CY Retarder:SYAD 75 - 2 OZ/100#9.4 OZ/CY (IF NECESSARY) RITEKS A-TRAIN - .32 OZ/100 NEXCRETE 1710 - 5 OZ/100# 13020AE - 5 SACK RITEKS -A-TRAIN, NEXCRETE WR BIG D CONCRETE CONCRETE STRENGTH REPORT AVERAGES:AIR SLUMP 7 - DAY 28 - DAY CONTENT STRENGTH STRENGTH MIX: 13020AE 3000 PSI 4.47 5.10 3,680 4,809 ABOVE REQUIRED:1,809 122.67%160.29% TEST CYL.TESTING DATE TICKET AMBIENT MIX AIR SLUMP 7 - DAY 28 - DAY 28 - DAY 28 - DAY 28 - DAY NO.NO.AGENCY CAST NO.TEMP.TEMP.CONTENT STRENGTH STRENGTH STRENGTH STRENGTH STRENGTH CY 1 CY 1 CY 2 CY 3 AVG. 1 516-520 HOOPER 3/4/16 57544 60 72 5.2 4.25 3,920 5,250 5,190 5,250 5,230 2 1,2,3,4 TERRACON 3/18/16 58061 63 70 3.9 4.00 3,750 5,190 5,250 5,120 5,187 3 1,2 D WITTWER 5/28/16 63949 72 78 4 4.50 3,867 4,340 4,104 4 1,2 D WITTWER 6/24/16 64203 88 90 5 5.00 4,239 4,470 4,355 5 1,2,3,4 PSI 6/24/16 64266 84 94 4.5 4.50 2,880 3,940 4,070 4,650 4,220 6 1,2,3,4 PSI 6/24/16 64275 84 94 4.6 5.75 2,860 4,830 4,690 4,940 4,820 7 1,2,3,4 PSI 6/24/16 64283 85 94 4.2 4.50 3,400 4,900 4,170 4,730 4,600 8 1,2,3,4 PSI 6/24/16 64299 84 92 4.2 4.75 3,660 5,230 4,930 5,290 5,150 9 1,2 D WITTWER 6/26/16 64692 82 86 5.5 5.00 3,981 4,183 4,082 10 1,2,3,4 PSI 7/29/16 66038 85 86 3.8 4.75 3,300 4,580 4,560 4,520 4,553 11 1,2,3,4 PSI 7/29/16 66060 88 90 3.8 4.75 2,650 4,190 3,880 4,180 4,083 12 1,2 D WITTWER 7/29/16 66697 84 91 5.5 5.00 4,526 4,749 4,638 13 1,2,3,4 PSI 7/29/16 66750 82 90 5.4 4.75 3,140 4,420 4,520 4,380 4,440 14 1,2,3,4 PSI 7/29/16 66766 82 91 5.2 5.00 3,280 4,370 4,240 4,380 4,330 15 1,2,3,4 PSI 7/29/16 66797 84 92 4.5 5.00 2,980 4,190 4,130 4,280 4,200 16 1,2,3,4 PSI 8/4/16 67297 91 89 5 5.75 2,540 4,820 4,670 4,900 4,797 17 1,2,3,4 PSI 10/1/16 71124 82 75 4.1 5.75 2,990 4,170 4,020 4,190 4,127 18 1,2,3,4 HOOPER 10/21/16 72187 70 71 4 5.00 2,870 4,360 4,140 4,250 19 1,2 D WITTWER 10/26/16 454 80 81 3.2 6.00 4,380 4,687 4,534 20 30-33 HOOPER 11/3/16 619 72 77 3.4 5.25 5,030 6,010 6,360 6,185 21 1,2,3 D WITTWER 11/4/16 734 53 60 11 6.00 3,617 5,570 5,280 5,370 5,407 22 1,2 D WITTWER 11/15/16 992 52 60 7 5.00 4,081 4,490 4,286 23 1,2,3,4 TERRACON 12/6/16 2024 50 71 4.1 4.75 4,890 5,790 5,910 5,950 5,883 24 1,2,3,4 TERRACON 12/6/17 2022 50 70 4.4 5.00 5,110 5,540 5,620 5,660 5,607 25 1,2,3 TERRACON 3/2/17 3824833 65 71 5 4.90 2,860 4,230 3,980 4,105 26 1,2,3 D WITTWER 4/1/17 9232 58 65 4.8 5.50 2,890 4,370 4,510 4,690 4,523 27 1,2,3,4 GLOBE 3/16/17 75408 61 70 3 4.00 4,600 4,980 5,570 5,640 5,397 28 1,2,3,4 GLOBE 3/21/17 127420 67 76 3.1 4.00 4,830 5,620 5,630 5,670 5,640 29 1,2,3,4 GLOBE 3/21/17 127437 66 76 3.7 4.50 5,230 5,650 5,660 5,660 5,657 30 1,2,3,4 GLOBE 3/21/17 127451 69 74 4 5.00 4,160 5,610 5,630 5,640 5,627 31 1,2,3,4 GLOBE 3/21/17 127466 70 73 4.2 4.80 4,150 5,640 5,640 5,660 5,647 32 1,2,3,4 GLOBE 3/23/17 127645 77 77 3.4 5.00 3,250 3,790 4,360 4,520 4,223 33 1,2,3,4 GLOBE 3/30/17 9043 57 77 3.6 4.50 4,230 34 1,2,3,4 GLOBE 3/30/17 9060 55 77 5.7 5.00 3,830 35 1,2,3,4 GLOBE 3/30/17 9071 54 75 3.5 4.00 3,290 36 1,2,3,4 GLOBE 4/14/17 10006 66 79 3.7 6.80 4,790 37 1,2,3,4 GLOBE 4/14/17 10017 66 78 3.3 6.50 2,950 38 1,2,3,4 GLOBE 4/14/17 10027 68 79 4.3 6.30 3,530 39 1,2,3,4 GLOBE 4/14/17 10043 70 80 3.3 7.00 3,330 40 1,2,3,4 ECS 4/17/17 10226 72 72 4.6 6.00 4,340 4.47 5.10 3,680 AVERAGE 4,809 AIR TEMP MIX TEMO AIR %SLUMP 122.67%% ABOVE REQUIRED:160.29% We warrant our products to be of good quality and will replace or, at our discretion, refund the purchase price of any products proved defective. Satisfactory results depend not only upon quality products, but also upon many factors beyond our control. Therefore, except for such replacement or refund, RITEKS MAKES NO WARRANTY OR GUARANTEE, EXPRESS OR IMPLIED, INCLUDING WARRANTIES OF FITNESS FOR A PARTICULAR PURPOSE OR MERCHANTABILITY. Riteks shall have no other liability with respect thereto. User shall determine the suitability of the products for the intended use and assume all risks and liability in connection therewith. The information provided herein is based on technical data that Riteks, Inc. believes to be reliable. Riteks, Inc. makes no representation or warranty as to the completeness or accuracy thereof and assumes no liability resulting from its use for any claims, losses, or damages of any third party. Recipients receiving this information must exercise their own judgment as to the appropriateness of its use and it is the user’s responsibility to assess the material’s suitability (including safety) for a particular purpose prior to such use. 415 Interchange St. McKinney, TX 75071 Ph: [972] 529-1118 • Fax: [972] 548-1790 www.riteks.com Technical Data Sheet Riteks™ Construction Admixture Chemicals General Description SYAD™ 75 is a retarding admixture recommended for all concrete where extended setting characteristics, particularly in hot weather are desired. SYAD 75 delays time of set to accommodate long haul times, or facilitate placement and finishing during hot weather concreting. Primary Applications SYAD 75 was designed to be used where an economical and effective retarding is required to offset the accelerating effects of high ambient temperature concreting. SYAD 75 will delay initial set times allowing proper placement and finishing without cold joints in hot weather conditions. Features / Advantages • Delays setting characteristics • Improves workability and finishability • Excellent retarding properties How to Use / Dosage Mixing: SYAD 75 should not come into contact with dry cement or other admixtures until they are mixed. Dosage: Rates will vary depending on the materials used, ambient conditions and the requirements of a specific project. For best results, add SYAD 75 to the water and aggregate mix at between 1.5-3 fl. oz of 100 lbs. of cementitious materials. Due to variations in concrete materials, job site conditions and applications, dosages outside of the recommended range may be required. In such cases, contact your local Riteks Construction Chemical Representative. Note: SYAD 75 does not contain calcium chloride or any chloride-based components and is non-corrosive to reinforced, galvanized floor/roof systems or prestressing steel. Specifications Conforms to: ASTM C 494 Type B Health and Environmental Data Please refer to the Material Safety Data Sheet for complete health, safety and environmental information. Packaging / Shelf Life 5 gallon pail • 55 gallon drum Totes • Bulk deliveries Store between 32° F and 100° F. Product should be used within 12 months of delivery. SYAD™ 75 Retarding Admixture Product Specification TxDOT Conc Agg Gr 4 (1") ASTM C33 Fine Agg_Manufact ured 057 Concrete Grade 4 30931 Manufactured Sand Plant 342 Weatherford Quarry 342 Weatherford Quarry 1 1/2" (37.5mm)100.0 1" (25mm)96.3 3/4" (19mm)76.1 1/2" (12.5mm)40.5 3/8" (9.5mm)20.7 100.0 #4 (4.75mm)3.4 99.8 #8 (2.36mm)0.6 88.5 #16 (1.18mm)53.0 #30 (0.6mm)30.7 #50 (0.3mm)15.8 #100 (0.15mm)6.8 #200 (75µm)4.09 Pan 0.00 0.00 Coarseness Factor 79.8 0.0 Workability Factor 0.6 88.5 -#200 (75um)0.60 4.08 Grad Loss 0.010 0.028 D10 (ES)6.71 0.20 D15 7.98 0.28 D15/D85 0.38 0.13 D50 13.93 1.08 D60 15.69 1.35 D85 21.17 2.22 Cc 1.13 1.26 Cu 2.41 7.07 SE 88 FM 6.97 3.05 Absorption 0.8 1.3 SPGR (Dry,Gsb)2.655 2.648 SPGR (SSD)2.677 2.684 SPGR (Apparent,Gsa)2.714 2.746 Unit Wt (Loose)90 92 Unit Wt (Rodded)100 104 Unit Wt SSD (Loose)90 93 Unit Wt SSD (Rodded)100 103 Voids (Loose)47 44 Product Quality Summary Report Period 02/23/2015 - 02/23/2017 1Page:ofVulcan Materials Company 3StonemontQC02/23/2017