PA1501B-DR170426
DAILY CONSTRUCTION REPORT
DATE ___04/26/2017___ REPORT #________________
PROJECT: Andrew Brown
DAY
M T W T F S S
PROJECT NO.
WEATHER Overcast
OWNER CITY of COPPELL
TEMP 63
WIND NW 24
CONTRACTOR: CORE
HUMIDITY 78
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
West
-The contractor is still working on the landscaping
East
-Miller Sierra is tying steel for the next section of walking area
-CORE is still working on the retaining wall for the far east pavilion
-Nema Electric is still working on the pavilion
-CORE is working on the center pavilion
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.
DAILY CONSTRUCTION REPORT
REPORT #_____________
Page _____ of _____ pages.