PA1501B-DR170522
DAILY CONSTRUCTION REPORT
DATE ___05/23/2017___ REPORT #________________
PROJECT: Andrew Brown
DAY
M T W T F S S
PROJECT NO.
WEATHER Light
Shower
OWNER CITY of COPPELL
TEMP 73
CONTRACTOR: CORE
WIND NW 16
HUMIDITY 56
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
West
East
-The landscapers are onsite installing sod
-The northern pavilion is being worked on
-NEMA electric is still working on the pavilions
-The bridge is still being bricked
-CORE plans to be finished in 2 weeks
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.
DAILY CONSTRUCTION REPORT
REPORT #_____________
Page _____ of _____ pages.