PA1501B-DR170524
DAILY CONSTRUCTION REPORT
DATE ___05/24/2017___ REPORT #________________
PROJECT: Andrew Brown
DAY
M T W T F S S
PROJECT NO.
WEATHER Sunny
OWNER CITY of COPPELL
TEMP 75
WIND NW 16
CONTRACTOR: CORE
HUMIDITY 37
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
West
East
-Sod is still being installed on the park
-The water meter is being adjusted to the proper height
-Brick is still being installed
-The north and south pavilion are still being worked on
-I informed Robert from CORE that the irrigation meters need to be raised
-The domestic water meter were installed correctly
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.
DAILY CONSTRUCTION REPORT
REPORT #_____________
Page _____ of _____ pages.