PA1501B-DR170531
DAILY CONSTRUCTION REPORT
DATE ___05/31/2017___ REPORT #________________
PROJECT: Andrew Brown
DAY
M T W T F S S
PROJECT NO.
WEATHER Partly
Cloudy
OWNER CITY of COPPELL
TEMP 91
CONTRACTOR: CORE
WIND ESE 9
HUMIDITY 34
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
West
East
-CORE is finishing the Sod on the sight
-Trees are still being planted
-No work has started on the pavement repairs
-Electrical work is being done on the pavilions
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.
DAILY CONSTRUCTION REPORT
REPORT #_____________
Page _____ of _____ pages.