CRDC1401-CS170523
DAILY CONSTRUCTION REPORT
DATE ___05/23/2017____ REPORT #________________
PROJECT: Denton Tap/Sandy Lake
DAY
M T W T F S S
PROJECT NO.
WEATHER Light
Shower
OWNER CITY of COPPELL
TEMP 78
CONTRACTOR: Pavecon
WIND NW 16
HUMIDITY 56
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
-AALC is working on the landscaping in the median west of Freeport
-The letters on the monuments will be changed
-Mr. Zbranek checked the light pole
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.