Prologis Park-DR170524
DAILY CONSTRUCTION REPORT
DATE ___05/24/2017_12:30pm__ REPORT #________________
PROJECT: Building 3
DAY
M T W T F S S
PROJECT NO.
WEATHER Sunny
OWNER Prologis
TEMP 75
WIND NW 16
CONTRACTOR: Mycon
HUMIDITY 37
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
-Potter is de-watering the north side of the property
-Mycon is still painting the exterior of the building
-Mycon plans to start working on the re-vised retaining walls
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.