Prologis Park-DR170524 DAILY CONSTRUCTION REPORT DATE ___05/24/2017_12:30pm__ REPORT #________________ PROJECT: Building 3 DAY M T W T F S S PROJECT NO. WEATHER Sunny OWNER Prologis TEMP 75 WIND NW 16 CONTRACTOR: Mycon HUMIDITY 37 PROJECT INSPECTOR: Marcus Marion AVERAGE FIELD FORCE NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: -Potter is de-watering the north side of the property -Mycon is still painting the exterior of the building -Mycon plans to start working on the re-vised retaining walls SIGNATURE PUBLIC WORKS INSPECTOR Page _____ of _____ pages. DAILY CONSTRUCTION REPORT REPORT #_____________ Page _____ of _____ pages.