Connell Skaggs Addition-CS171017 ■•■ HALFF
3803 Parkwood Blvd., Ste 800
Frisco,Texas 75034
■■■ (214)618-4570
Fax(214)618-4574
LETTER OF TRANSMITTAL
To: City of Coppell Date: October 17, 2017
Engineering Department
Attn: George Marshall
265 Parkway Blvd.
Coppell TX, 75019
From: Brian Satagaj AVO: 32293
Email: bsatagaj(a�halff.com Project: Woodside Village
Phone: 214.217.6463 Connell Skaggs Addition
Lot 1 R, 3R1 & 3R2, Block 1
3rd Engineering Submittal
WE ARE SENDING YOU ®Attached
® Plans ® CD/DVD
VIA: ®Courier
THESE ARE TRANSMITTED as checked below:
® For Review/Approval
ITEMS SENT:
• 2—24"x 36"Construction Plan Set
• 1 —Comment Response
• 1 —CD containing the above items in PDF format
COMMENTS:
If you have any questions please contact me at(214) 217-6463
SIGNED: BRIAN M.SATAGAJA�� �?
COPIES:
® File ❑ Owner ❑ Contractor ❑ Other:
Connell Skaggs Full Plan Set 2nd_06162017_v2.pdf Markup Summary
Markup Page Label Author Comments
14(4)
1 14 gmarshall Adjust meter locations so public side is outside the pavement.
2 vim: ,. 14 dzbranek <ID:4>Add FH install note
Sta xxxxxx
Fittings
Valves
1 - Fire Hydrant Assembly Per City of Coppell Standard Construction Detail 4120
3 ; 14 mgarza <ID:1>can we keep these service runs outside of the pavement.
4 14 mgarza <ID:1>is there an easement for these meters?or move the meters to the ROW.
I
17(2)
5 "1-1" 17 gmarshall Pre-cast screening wall is unacceptable for Coppell.
The engineering department is reviewing the wall foundation for impact to existing
drainage system.
6 _ 17 gmarshall Provide a detailed plan view that shows the location of property lines and existing
features like storm drain,and other utilities. Including any impacts to trees in the
area.
Comment Response Prepared by: Brian Satagaj
Comment Response Prepared on: 10/16/2017
1. Meter locations adjusted to keep public side out of pavement per additional City coordination.
2. Plan note adjusted with arrow pointing to tee location of hydrant lateral and hydrant location.
3. Meter locations adjusted per item 1. The remaining under pavement run is private.
4. Meter locations adjusted per item 1. Proposed easement placed around water meters.
5. Revised screen wall plans (by others) included in Civil package. Based on additional coordi
nation between Owner and City we believe the proposed wall to be in compliance with City stan
dards. Drainage revisions shown based on impacts to existing drainage system and inlets. Ex
isting curb inlets in conflict with screen wall to be replaced with new curb inlets. Drainage calcu
lations updated to verify capacity of proposed inlet system.
6. A plan view has been included in the screen wall plans (by others). Additional plan notes
added to Paving Plan regarding direction to contractor.
Connell Skaggs Full Plan Set 2nd_06162017_v2.pdf Markup Summary
Markup Page Label Author Comments
14(4)
14 gmarshall Adjust meter locations so public side is outside the pavement.
2 14 dzbranek <ID:4>Add FH install note
Sta xxxxxx
Fittings
Valves
1 - Fire Hydrant Assembly Per City of Coppell Standard Construction Detail 4120
3 `_ 14 mgarza <ID:1>can we keep these service runs outside of the pavement.
4 14 mgarza <ID:1>is there an easement for these meters?or move the meters to the ROW.
17(2)
Now
5 ' 17 gmarshall Pre-cast screening wall is unacceptable for Coppell.
The engineering department is reviewing the wall foundation for impact to existing
drainage system.
6 - 17 gmarshall Provide a detailed plan view that shows the location of property lines and existing
- features like storm drain, and other utilities. Including any impacts to trees in the
area.
Comment Response Prepared by: Brian Satagaj
Comment Response Prepared on: 10/16/2017
1. Meter locations adjusted to keep public side out of pavement per additional City coordination.
2. Plan note adjusted with arrow pointing to tee location of hydrant lateral and hydrant location.
3. Meter locations adjusted per item 1. The remaining under pavement run is private.
4. Meter locations adjusted per item 1. Proposed easement placed around water meters.
5. Revised screen wall plans (by others) included in Civil package. Based on additional coordi
nation between Owner and City we believe the proposed wall to be in compliance with City stan
dards. Drainage revisions shown based on impacts to existing drainage system and inlets. Ex
isting curb inlets in conflict with screen wall to be replaced with new curb inlets. Drainage calcu
lations updated to verify capacity of proposed inlet system.
6. A plan view has been included in the screen wall plans (by others). Additional plan notes
added to Paving Plan regarding direction to contractor.