WA9302-CN 960924 CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
PROJECT: Village Parkway 2nd Ground Storage Tank / WA 93-02
CONTRACTOR: NATGUN Corporation
OWNER: City of Coppell
CHANGE ORDER NO.: 1 DATE: 9/23/96
CHANGE OR EXTRA WORK TO BE DONE
Item Description Quantity Unit Unit Price Total
ADD: 1 Reroute conduit and 1 LS 2,843.40 $2,843.40
extend Circuit 150'
including overhead and
profit
Total Revision to Contract Amount $ 2,843.40
Previous contract amount $ 2,809,305.00
Net increase in contract amount $ 2,843.40
Revised contract amount $ 2,812,148.40
Net increase in contract time of completion N/A
Revised Contract time of completion N/A
The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full
accord and satisfaction of all past and future liability originating under any clause in the Contract
by reason of this revision to the Contract.
the Owner: Date: 9-24-96
'89/23/i996 i3:15 2i436i82Jai SHIMEK,JACOBS&FINKLE PAGE 03/~G
CITY OF COPPELL, TEXAS
VILLAGE PARKWAY GROUND STORAGE RESERVOIR NO. 2
CHANGE ORDER NO. 1
A. INTENT OF CHANGE ORDER
The intent of this change order is to modify the provisions of the contract entered into between the City of
Coppell, Texas and Natgun Corporation, 11 Teal Road, Wakefield, Massachusetts 01880-12592, for
construction of the Village Parkway Ground Storage Roservoir No. 2, dated May 23, 1995.
B. DESCRIPTION OF.,CHANGE
Change Order No. 1 covers the additional work required to re-route the conduit feeding the pole lights on the
Village Parkway Ground Storage Reservoir No. 2 and extend the circuit by 150 feet. The construction
record drawings for the pump station showed a power conduit installed under the concrete drive around the
existing tank. Apparently, the conduits were not installed as shown. The City of Coppell will reimburse
Natgun Corporation for the additional work in the lump sum mount shown below.
C. EFF~C..T. OF CHANGE ON CONTRACT A~MOUNT
This change order will have the following effect on the cost of this project:
Item ...... ]Original Quantity ] Revised ~ Unit Amount
No. , Description , , Quantity Th~ C.O. Quantity Unit Pr~c,e of Change
I Re-route Conduit and Extend Circuit 0 I 1 L.S. $2,843.40 $2,843A0
150 feet including Overhead and Profit
Total: $2,843.40
Original Contract Amount $2,809,305.00
Amount, Change Order No. 1 $2,843.40
Revised Contract Amount $2,812,148.40
D. EFFECT_OF CHANGE ON CONTRA, CT TLME
The work required under this change order will add no additional calendar days to this project.
Original Contract Time 300 calendar days
Time, Change Order No. 1 0 calendar days
Revised Contract Time 300 calendar days
9.,2r1,'96 Page ] of 2
' FAX I Pmt~ September 20, 1996
Number ofpege~ inCludin~l cover ~eer
TO: Gary C. Hendricks
Shimek, Jacobs & Finklea FROM: Anthony L. DiGiovanni
Suite 820 Natgun Corporation
8333 Douglas Avenue 11I Teal Road
Dallas, Texas 75225 Wakefield, MA 01880
RE: Coppail, Texas Project
I~hone 214-361-7900
Fax Phone 214-361-0204 l~hone 6f 7.224-5135
Fax Phone 617-224-5153
REMARKS: [] Urgent [] For your review [] Reply ASAP [] Please Comment
Attached is the extra cost fOrm-routing electrical conduit to the pole ligh! on the above referenced
project. The total cost for this work is $2.843.40 and breaks down as follows:
Abre Service Company $2.708.00
Natgun 0 & P (5%) 135_40
$2,843.40
We would appreciate your immediate attention in approving a change order. If you have any
question, please give us a call.
Attachment
Pc sox 540e0e
Oallss, TX 75220
Phone: (Zl&) 350~5721 Fax: (214) 350-0839
DATE: SEPTEMBER 19. 1996
TO: NATGUN CORPORATION
ELEVEN TEAL ROAD
WAKEFIELD, HA 01880-1292
ATTN: MR. FREDRICK A. MCDONOUGH JR.~'~
VICE-PRESIDENT-CONSTRUCTiON TT'A,/. -Z]'C)~
FROH: GAYLON MCKNIGHT
ESTIMATOR/PROJECT MANAGER
RE: 6.0 MG VILLAGE PARKWAY GROUND STORAGE RESEVOIR NO. 2
PROJECT No. WA-9302
COPPELL, TEXAS
TO RE-ROUTE THE CONOUIT FEEDING THE POLE LIGHTS ON THE REFERENCED
PROJECT AND EXTEND THE CIRCUIT BY 150 FT,, WE SUBMIT THE SUM
$2.708.00
SCOPE OF WORK~
FURNISH & INSTALL;
150 FT, OF 1" PVC COATED RIGID CONDUIT WiTH THE WIRE, FITTINGS,
SLICE KITS, AND ROCK TRENCHING REQUIRED
=iNCLUDES= 1) PERMIT, LICENSE, AND INSURANCE
~) COMPLIANCE WITH THE NATIONAL ELECTRIC CODE ,CITY
AND STATE LAWS AND OR01NANCE5
PLEASE ADVISE BY CHANGE ORDER TO OUR CONTRACT IF YOU WiSH FOR US TO
PROCEED WITH THIS CHANGE IN OUR SCOPE OF WORK.
SINCERELY,
ABLE SERVICE COMPANY
GAYLON MCKNIGHT