Matthew P. Kostial, P.E. Oracle
Engineering 2204 Green Hill
Dr McKinney, TX 75070
RE: Lost Creek Addition Lot 26R Block 1
Construction Plan Review Comments
The City of Coppell has reviewed the referenced plans and has the following comments to offer:
General Comments
1) Include Lost Creek Addition Lot 26R, Block 1 on the cover sheet.
Revised
Paving Plan
2) Will need to revise site plan as approved by City to construct as designed.
a) The on-street parking showed islands previously.
Revised
b) The sidewalk was T wide previously
Revised
3) Show correct property owner to the south.
Revised
4) No curb along paving adjacent to mutual access easement & pave to property line.
Revised
5) On street parking will need to be 8" with#4 bars 18" OC. With lime stabilization as city standard.
Noted
6) Sidewalks wider than 6'need to be 6" thick
Noted
7) I believe you will need truncated domes for the access to the handicap spot.
Noted
8) It appears the parking stalls are a little short. Should be at least 18'measured face to face
perpendicular to roadway.
18'
9) If this is truly live-work then the parking lot in the rear should be treated like a commercial parking
lot. I.E. curb radius larger than 5'. Provide stamped concrete at the entrance.
Revised
10)Be sure to keep handicap signage out of sidewalk.
Noted
11)Minimum sidewalk widths are now 5'. Along Heath Ln it is show to be a 4' walk.
Revised
12)The sidewalk transition at the intersection of Heath needs to be more fluid and not so abrupt. (90°).
Revised
Grading Plan
13)Show top of curb elevations along Heath Lane and Coppell Road. Very little detail shown.
Revised
14)Show proposed grades at all PCs, PTs and PCIs.
Revised
15)Detail grading for handicap spots better.
Revised
16)Provide collection for runoff in the side of the lot on the south and east side.
Revised
17)Revise existing ground contours (dashed?).
Revised
Drainage Area Map
18) If the roof drains are directly connected to the storm sewer, doesn't this affect the time of
concentration?
We're already using a commercial time of concentration of 10 minutes.
19)Provide plan and profile with HGL for private storm sewer.
Revised
a) Show the capacity in the downstream storm sewer pipe
Revised
Water and Sanitary Plan
20) 1 - 4" sewer service cannot serve 3 buildings. Revise.
Revised
a) You can probably bore directly into the manhole in Coppell Road without tearing up the
pavement. Connect the southern 2 buildings to the south and keep the northern building to the
existing service.
Revised
21) 1 - 2" domestic service is not acceptable with this type of construction. Each building needs
their own meter and you will probably need another to serve Irrigation.
Revised
22) Show City of Coppell 2" conduit for fiber optic that was built with Coppell Road.
Revised
Private Civil Details
23) Where is the curb stop being placed?
Revised
24)You will still be required to use City Details for SWPPP
Noted
There are other minor comments made throughout the construction plans. Please make the
necessary changes and submit these marked-up plans and two sets of revised plans to the
City for review. If you have any questions or would like to meet with city staff to address
these issues, please contact this office at your convenience.
Sincerely,
George Marshall, P.E.
Engineering Manager
Office Phone: (972) 304-
3562
gmarshall@coppelltx.gov