Tax2013B- CS160601 CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
PROJECT: Highland Meadow Circle TAX 2013B
CONTRACTOR: CD Builders,Inc.
OWNER: City of Coppell
CHANGE ORDER NO.: Two(2) DATE: July 8,2016
1. This change order provides for adjustment of scope to correspond with the work required in the field
2. This change order adds two(2)days to the contract
Item Description Quantity Unit Unit Price Total
Add: 99 Tree Removal in conflict 1 EA $1,416.00 $1,416.00
with Sidewalk
100 2" Irrigation to Cul De Sac 1 EA $3,261.45 $3,261.45
Total Additions $4,677.45
Delete:
Total Deletions $0.00
Total Revision to Contract Amount: $4,677.45
Original contract amount
$2,376,151.00
Net increase in contract amount $4,677.45
Previously approved changes $8,509.70
Revised contract amount $2,389,338.15
Cumulative increase in TOTAL change order amount(Percentage) 0.6%
Net increase in contract time of completion(This Change Order) 2
CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
Revised Contract time of completion(Including Previous Changes) 254
The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and
Recommended by City Engineer Date
Agreed to by Contractor Date