Dallas County-CS171205 (2)
Priscilla Martinez
From:Marcus Marion
Sent:Wednesday, December 06, 2017 3:53 PM
To:Priscilla Martinez
Subject:Campion Trail
Attachments:schematic cross section.pdf
The schematics cross section for Campion Trail
From: Gene Moulden \[mailto:GMoulden@cityofirving.org\]
Sent: Tuesday, December 5, 2017 5:00 PM
To: George Marshall <GMarshall@coppelltx.gov>
Cc: John Elias <JElias@coppelltx.gov>; Darryl Zbranek <dzbranek@coppelltx.gov>; Marcus Marion
<MMarion@coppelltx.gov>
Subject: RE: Campion Trail - Survey
George,
I went back out to the site after our meeting and wanted to see if the attached cross section at STA 123+50 would be a
possibility.
It would keep the existing alignment and dip down into the drainage way. It would use 18” rip-rap for slope protection.
It has its pros and cons, but thought it could be considered.
Gene Moulden | Planning Manager
City of Irving |Capital Improvement Program
825 W. Irving Blvd. Irving, TX 75060
P: (972) 721-2719 C: (469) 446-4308
gmoulden@cityofirving.org | CityofIrving.org
From: George Marshall \[mailto:GMarshall@coppelltx.gov\]
Sent: Tuesday, December 05, 2017 4:12 PM
To: Gene Moulden
Cc: John Elias; Darryl Zbranek; Marcus Marion
Subject: Campion Trail - Survey
Gene,
We would not be able to get you anything before next Friday at the earliest.
If you want us to proceed, let me know.
Thanks, George
1
George S. Marshall, P.E.
Engineering Manager
Engineering & Public Works
City of Coppell, TX
972-304-3562 (office)
469-964-4731 (cell)
www.coppelltx.gov