WA9302-CS 951114SHIMEK, JACObS FINKLEA CONSTRUCTION REPORT Project No. 94 ss Date: 11-14-9S Prepared ~i~ Is This A By: Ma~ Hiekey ~ ] }/ Working Day? ~ Yes ~ No Owner: Ci~ of Coppell Project Name: Village P~kway Ground Storage Rese~oir No. 2 ConsWuction Contractor: NATG~ Time AlloWed: 300 Used: 114 Number Superintendent: John Holroyd Men Working: 6 Hours: 9:00 AM to 9:30 AM Weather Conditions: Cle~ ~d Cool Site Conditions: The site was d~ and well maintained. WORK DESCRIPTION 1. The pier drilling operation is complete. 2. Work has begun on the tank outlet piping 3. A jack hammer was being used to remove the excess concrete from the pier caps. 4. The exposed steel reinforcement on the completed piers is being cut to 1' - 9" above the top of the piers. 5. The tank pad and job site were being cleaned and prepared for future tank construction.