WA9302-CS 951114SHIMEK, JACObS FINKLEA
CONSTRUCTION REPORT Project No. 94 ss
Date: 11-14-9S
Prepared ~i~ Is This A
By: Ma~ Hiekey ~ ] }/ Working Day? ~ Yes ~ No
Owner: Ci~ of Coppell Project Name: Village P~kway Ground Storage Rese~oir No. 2
ConsWuction
Contractor: NATG~ Time AlloWed: 300 Used: 114
Number
Superintendent: John Holroyd Men Working: 6 Hours: 9:00 AM to 9:30 AM
Weather Conditions: Cle~ ~d Cool
Site Conditions: The site was d~ and well maintained.
WORK DESCRIPTION
1. The pier drilling operation is complete.
2. Work has begun on the tank outlet piping
3. A jack hammer was being used to remove the excess concrete from the pier caps.
4. The exposed steel reinforcement on the completed piers is being cut to 1' - 9" above the top of the piers.
5. The tank pad and job site were being cleaned and prepared for future tank construction.