Loading...
WA9302-CS 951024SHIMEK, JACOBS. FINKLEA 7 CONSTRUCTION REPORT ProjeaNo. 94155 Date: 10-24-95 Prepared Is This A By: Matt Hiekey Working Day? [] Yes [] No Owner: City of Coppell Project Name: Village Parkway Ground Storage Reservoir No. 2 Construction Contractor: NATGUN Time Allotted: 300 Used: 93 Number Superintendent: John Holroyd Men Working: 10 Hours: 9:00 AM to 9:45 AM Weather Conditions: Clear and Cool Site Conditions: The site was dry and in good condition. WORK DESCRIPTION 1. Larry Davis wanted to know if the piers that were identified as 4 inches out of plumb were acceptable. * A letter will be issued to Larry Davis regarding the piers that were 4 inches out of plumb. 2. The excess soil created from the pier drilling operation has been removed from a portion of the tank pad. 3. Two hundred and seventy two piers are completed. * In last weeks construction report, there was a mistake in the reported number of piers completed. The new superintendent reported that two hundred seventy four piers were completed. 4. Two drilling rigs, one Bobcat, one backhoe, one lift and one Skytrack were in operation. 5. The piers are anticipated to be completed on October 31, 1995.