WA9302-CS 951017SHIMEK, JACOBS FINKLEA 7
CONSTRUCTION REPORT Pr,. o. 94155
Date: 10-17-95
Prepared Is This A
By: Matt Hiekey Working Day? [] Yes [] No
Owner: City of Coppell Project Name: Village Parkway Ground Storage Reservoir No. 2
Construction
Contractor: NATGUN Time Allotted: 300 Used: 86
Number
Superintendent: Roy Twombley Men Working: 18 Hours: 9:00 AM to 9:40 AM
Weather Conditions: Clear and Cool
Site Conditions: The site was dry and in good condition.
WORK DESCRIPTION
1. Larry Davis wanted to know if the revised estimate for testing by Richard Gee was completed so a meeting
could be set up.
* We are reviewing Richard Gee's revised estimate for testing and will schedule a meeting.
2. The excess soil created from the pier drilling operation was being removed from the tank pad. A Bobcat and
laborers were performing the work.
3. Steel workers were tying the steel pier cages together.
4. Two drilling rigs, one Bobcat, one backhoe, one lift and one Skytrack were in operation.
5. Two hundred and seventy four piers are completed.
We have completed and mailed the original Construction Project Report sent to the City by the U.S. Commerce
Department. We are enclosing a copy of the Construction Report for your records.