Loading...
WA9302-CS 951005SHIMEK, JACOBS ,,: FINKLEA CONSTRUCTION REPORT Project No. 94155 Date: 10-05-95 Prepared ~/// Is This A By: Matt Hiekey Working Day? [] Yes [] No Owner: City of Coppell Project Name: Village Parkway Ground Storage Reservoir No. 2 Construction Contractor: NATGUN Time Allotted: 300 Used: 72 Number Superintendent: Roy Twombley Men Working: 10 Hours: 9:00 AM to 9:55 AM Weather Conditions: Clear Site Conditions: The pad was muddy and the site was wet. WORK DESCRIPTION 1. One hundred thirty eight piers have been completed. 2. Larry Davis was concerned over the progress of the pier drilling and the associated testing. * Natgun and Richard Gee will be contacted to discuss overtime and cancellation charges that occurred during the testing period. 3. One drilling rig was being repaired. 4. Two drilling rigs, one lift, one backhoe, one Sky Track and one concrete truck were operating on the site.