Georgetown Plaza-CS 860515GINN, INC. CONSULTING ENGINEERS GEORGETOWN PLAZA PUNCH LIST Existing valve stack for Mockingbird cemented in by paving contractor. Dirt in stack. J2. Water meter for landscaping~raise and bring to grade~ 3. Backfill curb at fire hydrant. /4. Fire hydrant leaking. Locking mechanism for round meter box. 6. Fire hydrant leaking. ~ ~ 7. Replace/raise 8" valve stack. ~ ~ ~'¢*/~¢ ~& Inlet throat rough -- rejected. Need fire hydrant valve cap. N. 10. Grade dirt from around fire hydrant. 11. Clean trash piles and concrete piles. fl2. 6' combination inlet -- needs dirt graded for proper drainage. 13. 6' combination inlet -- epoxy/grout honeycomb in walls. ~14. Strip forms in future driveway and backfill. /15. Remove broken concrete curbs from site. 16. Curb and gutter section in future drive uplifted -- remove and replace. ~17. Route and seal construction Joints to handicap ramps in future drive. ~18. Inlet throat not to specifications -- opening not wide enough inside forms. / -~9. Inlet throat too rough -- concrete slober on inlet face and top - no expansion material. ~0. Inlet throat rejection -- concrete in invert -- forms in side -- cover missing. 21. First manhole -- dirt in inlet -- pull nails out of walls~~ 22. Second manhole -- wood in neck -- dirt in invert -- bricks turned wrongw way in adj. neck.~i~ ~ / 23. Third manhole -- brick in invert -- wood in neck adjustment -- brick 16135Preston Road · Sukel06,Dalla$,Tex~ 75248 * Phon¢214/~86-(~ll 24. -~mr~th manhole -- recheck can't locate. j25.~- concrete and debris in back lot (private property) remove from J26. Temporary electrical pole -- aerial drop over parking lot too iow. 27.J Traffic channelization devices for Samuels Boulevard.