WA9302-CS 950905 (2)SHIMEK, JACOBS .~ FINKLEA '~
CONSTRUCTION REPORT Project No. 94~55
Date: 9-5-95
Prepared Is This A
By: Matt Hiekey Working Day? [] Yes [] No
Owner: City of Coppell Project Name: Village Parkway Ground Storage Reservoir No. 2
Construction
Contractor: NATGUN Time Allotted: 300 Used: 44
Number
Superintendent: Men Working: Hours: to
Weather Conditions: Sunny and Hot
Site Conditions:
WORK DESCRIPTION
1. Runoff from the existing on site sprinkler system caused mud and standing water. A temporary driveway will be
constructed to alleviate the problem.
2. Drilled pier reinforcement is being constructed.
3. Twelve piers are completed.
4. One of the completed piers was removed due. The drilling company is going to try and remove the remaining
concrete from the pier hole and pour on Wednesday.
5. Two drilling crews are on the site.
6.