DAILY FIELD REPORT
TESTED FOR
PROJECT
J W L COMPANY
C/O UNZICKER, SCHNURBUSH,
& ASSOCIATES
DALLAS, TEXAS
LAKE WOOD ESTATES
COPPELL, TEXAS
DATE
06/15/93
OURREPORTNO.
92159-166
WEATHER: CLEAR
TEMPERATURE RANGE: 85
ALPHA Reprelefltlflve: R. W.
TO:
9O
06/15/93
THE ALPHA TECHNICIAN TRAVELLED TO THE PROJECT SITE AS REQUESTED 8Y THE
CLIENT'S REPRESENTATIVE, TO MONITOR PIER EXCAVATIONS.
SEVENTEEN PIERS WERE DRILLED AND PLACED WITH CONCRETE. THE TECHNICIAN CAST
ONE SET OF FOUR CONCRETE TEST SPECIMENS FROM THE PLACEMENT.
RESULTS OF PIER MONITORING ARE SHOWN ON THE ENCLOSED REPORTS.
COMPRESSION TEST RESULTS WILL FOLLOW ON A SEPARATE REPORT.
CONCRETE
ALL REQUESTED FIELD TESTS WERE PERFORMED AND TEST RESULTS WERE REPORTED TO
THE CONTRACTOR.
TECHNICIAN RETURNED TO THE LABORATORY UPON COMPLETION OF SCHEDULED TESTING.