Loading...
WA9302-CS 950829SHIMEK, JACOBS FINKLEA CONSTRUCTION REPORT .rojectNo. 94155 Date: 8-29-95 Prepared Is This A By: Matt Hickey Working Day? [] Yes [] No Owner: City of Coppell Prqject Name: Village Parkway Ground Storage Reservoir No. 2 Construction Contractor: NATGUN Time Allotted: 300 Used: 37 Number Superin'tendent: Men Working: Hours: to Weather Conditions: Sunny and Hot Site Conditions: WORK DESCRIPTION 1. Runoff from the existing on site sprinkler system caused mud and standing water. A temporary driveway xvill be constructed to alleviate the problem. 2. Drilled pier reinforcement is being constructed. 3. Three piers are completed. 4. One of the completed piers was removed due to the concrete drying before the next concrete truck arrived. The second batch that xvas delivered to the site was dry. The new pier shaft will be drilled an extra 9.5 feet. 5. Hail' of the pier locations xvere marked. 6. Electricity' to the site is being installed.