WA9302-CS 960109 (2)SHIMEK, JACOB , & FINKLEA
CONSTRUCTION REPORT Project No. 94155
Date: 1/9/96
Prepared Is This A
By: Matt Hickey 'V~, Working Day? [] Yes [] No
Date: 1/9/96
Owner: City of Coppell Project Name: Village Parkway Ground Storage Reservoir No. 2
Construction
Contractor: NATGUN Time Allotted: 300 Used: 171
Number
Superintendent: Jim Fisher Men Working: 20 Hours: 9:00 AM to 10:00 AM
Weather Conditions: Clear and Cool
Site Conditions: The site was well maintained.
WORK DESCRIPTION
1. One hundred eight of one hundred sixty eight dome panels have been poured.
2. Fifteen of thirty seven wall panels have been poured.
3. Scaffolding is being erected on the tank floor. It will be used for temporary support of the dome panels during
construction.
4. The standing water on the driveway near the office has been removed.
5. Wet conditions remain at various locations around the outer ring of the pad between the waterstop and the sponge
filler pad.