WA9302-CS 960130SHIMEK, JACOb ,,¢ FINKLEA
CONSTRUCTION REPORT Project No. 94155
Date: 1/30/96
Prepared ~C~-q-~ is This A
By: Matt Hickey Working Day? [] Yes [] No
Owner: City of Coppell Project Name: Village Parkway Ground Storage Reservoir No. 2
Construction
Contractor: NATGUN Time Allotted: 300 Used: 192
Number
Superintendent: Jim Fisher Men Working: 24 Hours: 9:15 AM to 10:00 AM
Weather Conditions: Cloudy and Cold
Site Conditions: The site was dry and well maintained.
WORK DESCRIPTION
1. All Cast in place dome and wall panels have been poured.
2. Twenty-four of the One Hundred Sixty Eight dome panels have been placed on the shoring system.
3. Dome panels in the casting beds were being sandblasted and prepared for erection.
4. Debris from the erection of the shoring system was being removed from the tank floor.