WA9302-CS 960206 (2)SHIMEK, JACOBS FINKLEA CONSTRUCTION REPORT Project No. 94155 Date: 2/6/96 Prepared % Is This A By: Matt Hickey ~ Working Day? [] Yes [] No Owner: City of Coppell Project Name: Village Parkway Ground Storage Reservoir No. 2 Construction Contractor: NATGUN Time Allotted: 300 Used: 199 Number Superintendent: Jim Fisher Men Working: 12 Hours: 1:30 PM to 1:50 PM Weather Conditions: Cloudy and Warm Site Conditions: The site was dry and well maintained. WORK DESCRIPTION 1. Ten wall panels are being erected.. 2. Seventy-two of the One Hundred Sixty Eight dome panels have been placed on the shoring system. 3. A representative from Thoro System took a sample of the paint from the existing ground storage tank. A color will be created to approximately match the color of the existing tank.