WA9302-CS 960206 (2)SHIMEK, JACOBS FINKLEA
CONSTRUCTION REPORT Project No. 94155
Date: 2/6/96
Prepared % Is This A
By: Matt Hickey ~ Working Day? [] Yes [] No
Owner: City of Coppell Project Name: Village Parkway Ground Storage Reservoir No. 2
Construction
Contractor: NATGUN Time Allotted: 300 Used: 199
Number
Superintendent: Jim Fisher Men Working: 12 Hours: 1:30 PM to 1:50 PM
Weather Conditions: Cloudy and Warm
Site Conditions: The site was dry and well maintained.
WORK DESCRIPTION
1. Ten wall panels are being erected..
2. Seventy-two of the One Hundred Sixty Eight dome panels have been placed on the shoring system.
3. A representative from Thoro System took a sample of the paint from the existing ground storage tank. A color
will be created to approximately match the color of the existing tank.