WA9302-CS 960213SHIMEK, JACObS & FINKLEA
CONSTRUCTION REPORT 'roje. No. 94155
Date: 2/13/96
Prepared Is This A
By: Matt Hiekey ~ Working Day? [] Yes [] No
Owner: City of Coppell Project Name: Village Parkway Ground Storage Reservoir No. 2
Construction
Contractor: NATGUN Time Allotted: 300 Used: 206
Number
Superintendent: Jim Fisher Men Working: 20 Hours: 9:10 AM to 10:00 AM
Weather Conditions: Clear and Cool
Site Conditions: The site ~vas dry and well maintained.
WORK DESCRIPTION
1. All wall panels are erected and in place. The steel plates between the wall panels were being installed.
2. One Hundred Sixty of One Hundred Sixty Eight dome panels have been placed on the shoring system.
3. The dome panel above the precast wall panel that will contain the inflow pipe will be placed on the shoring
system once the inflow pipe is put into the tank. The inflow pipe was being bolted together. The bolts at the
flanges of the inflow pipe will be painted to prevent corrosion.
4. The driveway at the pump station is being removed and electrical conduits are being located by the contractor for
the Village Parkway Pump Station Addition Project. Mr. Larry Davis showed concerns that heavy spring rains
may cause drainage problems that will allow water to get under the foundation of the pump station. Jim Fisher
indicated that debris along the natural drainage path to the concrete channel south of the tank site will be removed
and on site drainage along the tank will be provided and maintained at all times.
cc: Mr. Bob Barbarisi, Jr.