Loading...
WA9302-CS 960312SHIMEK, JACOt,3 FINKLEA CONSTRUCTION RE ORT Prepared ~ I ' "' By: Gary Hendricks F/ Owner: City of Coppel Project Name: Contractor: NATGUN Superintendent: Number Project No. 94155 Date: 3/12/96 ls This A Working Day? ~ [] No Village Parkway Ground Storage Reservoir No. 2 Construction Time Allotted: 300 Used: 234 Jim Fisher Men Working: 15+/- Hours: 9:00 AM to 9:45 AM Weather Conditions: Clear and Cool Site Conditions: The site was dry and well maintained. WORK DESCRIPTION 1. The 1/2" corewall shotcrete, and a portion of the 1st layer of wire is now in place. 2. Equipment is set up to continue the wire wrap, but no work was progressing on that part of the project during my site visit 3. General clean up around the tank site and inside the tank was underway. 4. The scaffolding was being dismantled. cc: Mr. Bob Barbarisi, Jr.