WA9302-CS 960312SHIMEK, JACOt,3 FINKLEA
CONSTRUCTION RE ORT
Prepared ~ I ' "'
By: Gary Hendricks F/
Owner: City of Coppel Project Name:
Contractor: NATGUN
Superintendent:
Number
Project No. 94155
Date: 3/12/96
ls This A
Working Day? ~
[] No
Village Parkway Ground Storage Reservoir No. 2
Construction
Time Allotted: 300 Used: 234
Jim Fisher
Men Working: 15+/- Hours: 9:00 AM to 9:45 AM
Weather Conditions: Clear and Cool
Site Conditions: The site was dry and well maintained.
WORK DESCRIPTION
1. The 1/2" corewall shotcrete, and a portion of the 1st layer of wire is now in place.
2. Equipment is set up to continue the wire wrap, but no work was progressing on that part of the project during my
site visit
3. General clean up around the tank site and inside the tank was underway.
4. The scaffolding was being dismantled.