CONSTRUCTION REPORT
Prepared
By: Matt Hickey ~N{N~V-~
Project No. 94155
Date: 3/19/96
Is This A
Working Day? [] Yes [] No
Owner: City of Coppell
Contractor: NATGUN
Superintendent: Jim Fisher
Project Name: Village Parkway Ground Storage Reservoir No. 2
Construction
Time Allotted: 300 Used: 241
Number
Men Working: 10+/- Hours: 2:00 AM tO 3:00 PM
Weather Conditions: Clear and Cool
Site Conditions: The site was dry and well maintained.
WORK DESCRIPTION
1. The first wire wrap was being put into place at approximately 17'-6" off the finished floor elevation.
2. General clean up around the tank site and inside the tank was underway.
3. The scaffolding was being removed from the tank and the job site.