WA9302-CS 960402SHIMEK, JACOb FINKLEA
CONSTRUCTION REPORT
By: Matt Hickey
Project No. 94155
Date: 4/2/96
Is This A
Working Day? [] Yes [] No
Owner: City of Coppell
Contractor: NATGUN
Superintendent: Jim Fisher
Weather Conditions: Clear and Cool
Project Name: Village Parkway Ground Storage Reservoir No. 2
Construction
Time Allotted: 300 Used: 255
Number
Men Working: 8 Hours: 10:00 AM tO 10:30 AM
Site Conditions: The site was dry and well maintained.
WORK DESCRIPTION
1. Sixty one prestressing wraps will be completed by the end of the day. Jim Fisher indicated that the prestress
wrapping should be completed by April 4, 1996.
2. The temporary wall manholes are being sealed.
3. The interior of the tank is being cleaned and is expected to be pressure washed next week.
4. The sixth exterior paint sample was applied to the existing tank. The City currently has not selected the exterior
color.
cc: Mr. Bob Barbarisi, Jr.