Loading...
WA9302-CS 960402SHIMEK, JACOb FINKLEA CONSTRUCTION REPORT By: Matt Hickey Project No. 94155 Date: 4/2/96 Is This A Working Day? [] Yes [] No Owner: City of Coppell Contractor: NATGUN Superintendent: Jim Fisher Weather Conditions: Clear and Cool Project Name: Village Parkway Ground Storage Reservoir No. 2 Construction Time Allotted: 300 Used: 255 Number Men Working: 8 Hours: 10:00 AM tO 10:30 AM Site Conditions: The site was dry and well maintained. WORK DESCRIPTION 1. Sixty one prestressing wraps will be completed by the end of the day. Jim Fisher indicated that the prestress wrapping should be completed by April 4, 1996. 2. The temporary wall manholes are being sealed. 3. The interior of the tank is being cleaned and is expected to be pressure washed next week. 4. The sixth exterior paint sample was applied to the existing tank. The City currently has not selected the exterior color. cc: Mr. Bob Barbarisi, Jr.