First United-LR 990224 · GEOTECHNIC~L ENGINEkKING
E GEE Consultants, Inc.
10046 Monroe Drive · Dallas, Texas 75229 · (214) 352-5433 · Fax i214) 352-6972
REPORTOF CONCRETE MIX INSPECTION
Repo~ Date: Februa~' 24, 1999 Date Concrete Placed: January 26, 1999 Standard 6"x12"
C'dent: First United Methodist Church of Coppell Area 28.27 Square Inches
Pro,eot: First United Methodist Church-Sanctuary Concrete Report No. 10
Coppell. Texas
Contrac:or: Strand Tech. [nc. Prmect Xo.. 298-0394
Concrete Suppher .md Plant: Mid-Cities
Location of Placement: Slab
X'iATF..I~ IAI~ ........ ssi> ~ .....
INSPECTION
DATA
5.1tx Nunmer: 68 Time Sample Batched: 12:!8 pln
Cement: Time Sampied: 12:50 pm
Fi:,' Ash: Sample Locanon: ~:5' N. & -~0' E ,ar SW zurner
Coarse -Xo,,reeate: Talck,'Ticket No: - '~
Intermediate Aggregate: Temperature:
.-\mbmnt Range: -0':F
Fro: Aggregate: Concrete Range: -2~F
.\d:mxture~,: Slump Range :inches~: ~;,"
Weather Conditi{m~,: Clear
Time Started: 10:i5 am
Time Completed: ,}5:45 pm
..\dale,_'. Water: 40 Gallons Sample A~r Content. % :: 2 %
Total Cubm Yards Placed: ~60
Required Strength, Lbs.. sq.:,n...'-.0t)0
FUMC 45 7 02.-'02.-'99 77,400 2,7::0
28
FUMC 46 6" 02;23..'99 115.080 4.070
FUMC 47 28 ..... ~
0,:.-_~..99 120,820 4._,0
FUMC 48 H HOLD
a.:..;TM ('-3:.-',"-34 ('-hz.'3 U ~.ess 'qotet~ O::~e:"* se! Cylinders Made By: SS
Re:v. ar~.~ and.'or Distrlbuuon:
cc: Ms. Lynn Joi~nson - First United Methodist Church
Mr. Charles Harper - Itarper Perkins Architects
Mr. Larry Davis - City of Coppell
Mr. Bill Anderson - Dowdey. Anderson & Ass(vciates. Inc.
Mr. Mel Fencl - Offult Construciton
GEOTECHNIC-~L ENGINEEKING
· GEE Consullants Inc.
CONSTRUCTION MATERIALS TESTING
10046 Monroe Drive · DaLlas, Texas 75229 · ~214) 352-5433 · Fax (214) 352-6972
REPORT OF CONCRETE MIX INSPECTION
Report Date: February 24. 1999 Date Concrete Placed: January 26. i999 Standard 6"x:2"
Cl,ent: First United Methodist Church of Coppell Area 28.27 Square Inches
Project: First United Methodist Church-Sanctuary Concrete Report No. 12
Coppell. Texas
Contractor: Strand Tech. Inc. Project ×o.. 298-0394
C.mcreEe Supplier and Plant: Mid-Cities
Locauon of Placement: Slab
LNSPECTION
DATA
Lbs. C'_Y~!,
5,hx Number: 68 Time Saxnple Batched: ill:r9 pm
Cement: Time Sampled: 02:05 pm
Fb' Ash: Sample Locauon: ;~..' "'~' N. ek 60' E of SW coruer
Truck:Ticket No: 760.'47334
Coarse Aggregate: Temperature:
Intermediate Aggregate: Ambient Range: .59:F
Frae Aggregate: Concrete Range: '72~F
.-\dnuxtures: Slump Range :inchest: 6"
Weather Conditions: Clear
" Time Started: i0:15 am
2 Time Completed: ,)5:-:5 pm
Added Water: it) Gallons Sample A~r Content, c:. ~: 2%
Ti}iai Cubic Yards Placed: 260
Required Strength , Lbs..'sq.in. ~: 3.000
FUMC 53 ? 02/02,:99 84,000 2.970
FUMC 54 28 02/23."99 109,260 3,860
6"
FUMC 55 28 02.'"23/99 ! 14,380 4,050
FUMC 56 H HOLD
res: .".letnlms Uta:zecl i rac:ure Regular Cylinders Made By: RB
Remarks and.:or Distribunon:
cc: Ms. Lynn Johnson - First United Methodist Church
Mr. Charles Harper - Harper Perkins Architects
Mr. LarD, Davis - City of Coppell
Mr. Bill Anderson - Dowdey. Anderson & Associates. Inc.
Mr. Mel Fencl - Offult Construciton
, G . GEOTECHNIC L ENGINEEKING
10046 Monroe Drive * Dallas, Texas 75229 · (214) 352-5433 * Fax {214) 352-6972
REPORT OF CONCRETE MIX INSPECTION
Report Date: February 24. 1999 Date Concrete Placed: Janual~.' 26, 1999 Stanoard 6"x12"
Client: First Untted Methodist Church of Coppell Area 28.27 Square Inches
Project: First United Methodist Church-Sanctuary Coocrete Repo.,x No. 15
Cov?q,. ~, . Texa:~
Contractor: Strand Tech, Inc. Project 5Io.: 298-0394
Concrete Supplier and P~ant: Mid-Cities
Location of Placement: Slab
MATERIALS ~ ....... ,so ~ ..... '*'~. LNSPECTION DATA
Mix Number: :,x Time Sample Batched: 04:03 Nm
Cement: Time Sampled: ,}4:55 pm
Fly Ash: Sample Locanon: 10' S. & 20' W of NE .:omer
Truck:Ticket Nu: -'.' 90..'47354
Coarse Aggregate: Temperature:
Intermediate Aggregate: :\mment Range: 69~F
Fine Aggregate: Concrete Range: 72=F
..\dmlxmres: Slump Range ~ mches~: 5 t ~ .'
Weather Conditions: C~ear
i Time Started: '.0:15 am
Time Completed: .}5:45 ~m
Added Water ,~ Gallons Sample Air Content. % ~: 2 :.': ~
Total Cubic Yards Placed: 440
Required Strength, Lbs. '.,q.m. ,: 3.000
FUMC 65 -7 02/02.'99 92.300 3,260
FUMC 66 28 02.'23:99 124,360 4.400
5%"
FUMC 67 28 02/23/99 131.320 4,650
FUMC 68 H HOLD
~.b'rM ('-3:.(.'-_;9.('-'43 k':t:ess No,ecl O:!~r~.,se, Cylinders Made By: SS
Remarks aod:or Distribuuon:
cc: Ms. Lynn Johnson - First United Methodist Church
Mr. Charies Harper - Harper Perkins Architects
Mr. Lar.,3: Davis - C:.ty of Coppell
Mr. Bill Anderson - Dowdey. Anderson & Assoc,ates. Inc.
Mr. Mel Fencl - Offult Construcnon
· GEOTECHNICAL ENGINEI:~,~NG
E o ENVIRONMENTALCONSULTING GEE Consultants, Inc.
I
E I · CONSTRUCTION ,MATERIALS TESTING
10046 Monroe Drive · Dallas, Texas 75229 · (214) 352-5433 · Fax (214) 352-6972
REPORT OF CONCRETE MIX INSPECTION
Report Date: February 24. 1999 Date Concrete Placed: JanuaD' 26. 1999 Standard 6"x12"
C'.iem: First United Methodist Church of Coppell Area 28.27 Square Inches
?ro~ect: First United Methodist Church-Sanctuary Concrete Report No. i4
Coppel!. Texas
Contractor: Strand Tech. Inc. Project .Xo.: 298-0394
Concrete Supplier and Plant: Mid-Cities
Locat,on of Placement: Slab
MATERIALS ........ ,so ,3 ....
INSPECTION
DATA
Mix Number: 68 Time Sample Batchea: 02:36 pm
Cement: Time Sampled: 03:25 pm
F!y Ash: Sample Locanon: 10' W. & 40' N of SE comer
Track/Ticket No: 556:47344
C,)arse Aggregate: Temperature:
Intermediate Aggregate: Ambient Range: 72~F
Fmc Aggregate: Ctmcrete Range: -'2°F
Afim:xtures: Slump Range - ~nci~es ,: 6 :.-:,"
: Weather Cono~unns: Clear
Time Started: 10:!5 :tm
2 Time Completed: ,15:45 pm
Added Water: ,~ Gallons Sample Air Content. %
Total Cuhm Yards Placed: 350
Reqmred Strength, Lbs.. sq. m. ~: 3.O00
FUMC 6 i -7 02/02/99 '7.,4.440 2.630
FUMC 62 28 02:23...'99 t00.700 3.560
FUMC 63 28 02/23!99 109.380 3.870
FUMC 64 H HOLD
-".bTM C-3:. C--:q C-:..:~ .'.':,less .".o:ee O,~:er'*-se, Cylinders .",lade By': aB
Remarks and;or Dismbut,on:
· .:ce Ms. Lynn Johnson - First United Methodist Church
Mr. Charles Harper - Harper Perkins Architects
Mr. Larry Davis - City of Coppell
Mr. Bill Anderson - Dowdey, Anderson & Associates. Inc.
Mr. Mel Fencl - Offult Construction
GEOTECHNICAL ENGINEERING
E [ GEE Consultants, Inc.
CONSTRUCTION ,MATERIALS TESTING
10046 Monroe Drive · Dallas, Texas 75229 · (214) 352-5433 ° Fax (214) 352-6972
REPORTOF CONCRETE MIX INSPECTION
Report Date: February 24, 1999 Date Concrete Placed: JallUal3: 26. 1999 Standard 6'x12"
Client: First United Methodist Church of Coppell Area 28..27 Square Inches
Prmect: First United Methodist Church-Sanctuaxx' Cancrete Report No. 13
Coppell. Texas
Contractor: Strand Tech. Inc. Proiect ×o.. 298-0394
Concrete Suppuer and Plant: Mid-Cities
Locanon of Placement: Slab
MATERIALS ...... ~so :.~:,,c,, ..,',, INSPECTION DATA
M~x Numoer: 68 Time Sample Batched: 01:48 pm
Cement: Time Sampled: 02:30 pm
F~v Ash: Sample Locatnm: 3()' W. & 55' Not SE comer
'Fmck~Ticket No: 557.-'5 !257
Coarse Aggregate: Temperature:
!ntermediate Aggregate: Ambieta Range: - 1 :: F
Fmc Aggregate: (?ancrete Range: '72:F
.-\dmtxtures: Slump Range inches~: q"
· Weather Condmons: Clear
Time Starteu: i0::5 am
Time Completed: ~}5:45 pm
Added Water- ,) Gailons Sample Air C.mtent q-.:
Total Cubic Yards Placed: 301}
Reqmred Strength, Lbs. sq.:ri.-: 5.000
FUMC 57 7 02.:02/99 74.300 2.630
FUMC 58 28 02/23."99 117.260 4.150
5"
FUMC 59 28 02,.'23:'99 115.520 4.090
FUMC 60 H HOLD
's, STM C-3:.C-31~ C-143 L',::es~, .Xa~ec {X~e'~,w, Cylinders Made By: RB
Remarks and..'or Distr~bunon:
cc: Ms. Lynn Johnson - First United Methodist Church
Mr. Charles Harper - Harper Perkins Archttects
Mr. Larry Davis - City of Coppell
Mr. Bill Anderson - Dowdey. Anderson & Associates. Inc.
Mr. N-lei Fend - Offult Construction
[ . GEOTECHNICAL ENGINEI:.I<ING
t GEE Consultants, Inc.
E i · CONSTRUCTION MATERIALS TESTING
0046 Monroe Drive · Dallas, Texas 75229 · (214) 352-5433 · Fax (214) 352-6972
REPORTOF CONCRETE MIX INSPECTION
Report Date: February 24. 1999 Date Concrete Placed: January 26. 1999 Stanuard 6"x 12"
Cl:ent: First United Methodist Church of Coppell Area 28.27 Square Inches
Pro~ect: First United Methodist Church-Sanctuary Concrete Report No. i l
Coppell. Texas
Contractor: Strand Tech. Inc. Project .Xo.: 298-0394-
Concrete Supplier and Plant: Mid-Cities
Locatmn ,ff P!acemem: Slab
X"IATF. RIAIq s ........ ' ~sr~ ,~ .....
INSPECTION
DATA
Mix Number: 6/i.. Time Samr>le. Batched: .... ~-.2_" pm
Cement: Time Sampled: 01:30 pm
Fly' A~-h: Sample Locanon: 65' N. & 50' E ff SW comer
Caarse Aggregate: Truck,-Ticket No: ~59.'47329
[:~termed:ate Aggregate: Temperature:
Ambient Range: ~2:F
F'.ne .-k,2tzro2ate: Gm, crete Range: ~2~F
Admixtures: Slump Range, mches~: ,')"
· Weamer C,mdmons: Clear
'rime Started: 10:15 :tm
Time Cmnpleted: 05:45 pm
Added Water- :1 Gailon.~ Sample A~r C,mtent ~% ,: 2 ~
It>mi Cubic Yards Placed: 200
Reqmred Strength, Lbs...3ti. m..: 3.000
FUMC 4-9 ? 02/02/99 66,960 2.370
FUMC 50 28 02,"23..'99 ', 11 !4-0 3,930
FUMC 51 28 02/23/99 91,380 3,230
FUMC 52 H HOLD
.V>TM :'-5! :'-'.,.~ r..'-;z3 L.";es~ Xlotea O:her,o.-~e, Cylinders Made By: SS
Remarks alld.'or DlStrlbu[ior!.:
cc: Ms. L;'nn Johnson - First Umted Methodist Church
Mr. Char[es Harper - Harper Perkins Architects
Mr. Larry Davis - City of Coppell
Mr. Bill Anderson - Dowdey. Anderson & Associates, Inc.
Mr. Mei Fencl - Offult Construction