Lakes of C 1stP-CS 860306 PUNCH LIST
March 6, 1986
LAKES OF COPPELL
Part A
1. MacArthur Boulevard/Village Parkway intersection Sta. 6+60
Rt. not draining properly.
2. MacArthur Boulevard/Village Parkway intersection Sta.30+40
Rt. not draining properly.
3. MacArthur Boulevard Sta. 34+00 Rt. east curb line not
draining properly.
4. Warren Drive/Village Parkway intersection not draining
properly.
5. Warren Drive random cracks not routed and sealed.
6. Dowel-on curb improperly constructed in 3rd median island
(busted off).
7. One-year maintenance bonds have not been received from
Jenson Construction Company.
8. As-built drawings showing add-on and deletion of
intersections and crossovers.
Part B - (V~llage Parkway)
1. Traffic buttons have not bonded to pavement.
A. 33 buttons south of box culvert need to be replaced.
B. 45 buttons north of box culvert need to be replaced.
2. One-year maintenance bonds from both contractors (Jaho
and Jensen).
3. As-built drawings.