CONSTRUCTION REPORT
Prepared
Project No. 94155
Date: 5/21/96
Is This A
Working Day? [] Yes [] No
Owner: City of Coppell
Contractor: NATGUN
Superintendent: Brian Phelp
Weather Conditions: Clear and Hot
Project Name: Village Parkway Ground Storage Reservoir No. 2
Construction
Time Allotted: 300 Used: 307
Number
Men Working: 6 Hours: 9:45am to 10:30am
Site Conditions: The site was well maintained.
WORK DESCRIPTION
1. Work has begun on the final application of the exterior coating system on the dome.
2. Brian Phelp indicated that Natgun will not load the tank until the exterior painting is complete. He indicated that
the entire tank will be painted by May 28, 1996, weather permitting.
3. Brian Phelp indicated that the items on the punch list that were the result of a May 13, walk-through were being
evaluated by Natgun
4. Repairs to the existing fence in the area around the outfall structure was in progress.
5. The outfall structure is in place.