WA9302-CS 960604SHIMEK, JACOb3 FINKLEA
CONSTRUCTION REPORT
Prepared
By: Matt Hickey
Project No. 94155
Date: 6/04/96
Is This A
Working Day? [] Yes [] No
Owner: City of Coppell
Contractor: NATGUN
Superintendent: Brian Phelp
Weather Conditions: Clear and Hot
Project Name: Village Parkway Ground Storage Reservoir No. 2
Construction
Time Allotted: 300 Used: 321
Number
Men Working: 1 Hours: 9:30am to 10:00am
Site Conditions: The site was well maintained.
WORK DESCRIPTION
1. Brian Phelps indicated that new paint samples were being delivered to the site. He said that he would paint a test
panel and place it near the existing ground storage tank.
2. The City directed Brian to take samples of the water inside to the tank to check the chlorine residuals.
3. Work had began to remove the Natgun's storage trailer from the jobsite.
cc: Mr. Bob Barbarisi, Jr.