WA9302-CS 960604 (2)SHIMEK, JACOb3 a. rINKLEA
CONSTRUCTION REPORT Project No. 94156
Date: 6/04/96
Prepared Is This A
By: Matt Hiekey Working Day? [] Yes [] No
Owner: City of Coppell
Project Name:
Contractor: North Texas Municipal Construction Co., Inc
Village Parkway Pump Station Addition
Construction
Time Allotted: 300 Used:
110
Number
Superintendent: Bill Bigham. Men Working: 2 Hours: 9:00 am to 9:30 am
Weather Conditions: Clear and Hot
Site Conditions: The site was reasonably clean and maintained
WORK DESCRIPTION
1. Two of the screening wall piers were in place.
2. Nine of the pump station piers were in place
3. The silt fences around the debris piles in the location of the proposed screening walls were not standing.
4. In preparation of painting the north side fence, the steel on the fence extension was being grinded.
5. Larry Davis showed concerns on the conditions of the interior of existing pump station. He indicated that the
interior must be cleaned to the conditions it was in before construction began.