Lake Park-CS 910510 COPPELL P~BLIC WOP~S 1991 Construction Inspector · oward Pafford, Water Utilities Superintendent Manhole Specifications for Lake Park Addition I have reviewed the specification documents regarding the Hydro Conduit Corp., precast manholes. I request the following changes in design prior to installation. 1) Ail joints are to be sealed with a layer of ram-neck sealer. 2) Ail manhole tops are to be of cone design. 3) Casted sections of the manhole must fall within one (I) foot of the finish surface grade of project. Also any extension of the cone must be made with concrete riser rings. 4) When using the positive seal gasket system as an alternate to the asbestos coupling (standard) the portion of the coupling outside the manhole must be encased in concrete to allow support of the pipe. Please insure these changes are made prior to installation. If you have any questions regarding this matter, please advise. HLP/mp cc= Steven G. Goram, Director of Public Works LAKEPRK. HLP