Loading...
WA9302-CS 960625SHIMEK, JACOt, S FINKLEA CONSTRUCTION REPORT Prepared ~ By: Matt Hickey Project No. 94155 Date: 6/25/96 Is This A Working Day? [] Yes [] No Owner: City of Coppell Contractor: NATGUN Superintendent: Roy Twombley Weather Conditions: Cloudy and Hot Site Conditions: The site was well maintained. Project Name: Village Parkway Ground Storage Reservoir No. 2 Construction Time Allotted: 300 Used: 342 Number Men Working: 1 Hours: 9:30am to 10:00am WORK DESCRIPTION Mr. Roy Twombley is Natgun's new superintendent. The outside access ladder has been installed. The superintendent showed Mr. Larry Davis additional paint samples for the final exterior coat. The City rejected the samples because they did not match the existing tank. Mr. Twombley said that additional samples were being prepared and could be possibly inspected on June 26, 1996. 4. The City accepted the light poles that were on site. We did not see the light fixtures. cc: Mr. Bob Barbarisi, Jr.