WA9302-CS 960625SHIMEK, JACOt, S FINKLEA
CONSTRUCTION REPORT
Prepared ~
By: Matt Hickey
Project No. 94155
Date: 6/25/96
Is This A
Working Day? [] Yes [] No
Owner: City of Coppell
Contractor: NATGUN
Superintendent: Roy Twombley
Weather Conditions: Cloudy and Hot
Site Conditions: The site was well maintained.
Project Name: Village Parkway Ground Storage Reservoir No. 2
Construction
Time Allotted: 300 Used: 342
Number
Men Working: 1 Hours: 9:30am to 10:00am
WORK DESCRIPTION
Mr. Roy Twombley is Natgun's new superintendent.
The outside access ladder has been installed.
The superintendent showed Mr. Larry Davis additional paint samples for the final exterior coat. The City rejected
the samples because they did not match the existing tank. Mr. Twombley said that additional samples were being
prepared and could be possibly inspected on June 26, 1996.
4. The City accepted the light poles that were on site. We did not see the light fixtures.
cc: Mr. Bob Barbarisi, Jr.