Freeport NIP(7.4)-LR000830 T$IT 2502 Gravel Drive - Ft. Worth, TX 76118 817-589-9933 Date: August 30, 2000 Report of Built-Up Roof lnspection PROJECT: Freeport Building VI Coppell, TX GENERAL CONTRACTOR: Hill & Wilkenson 800 Klien Rd. Suite 100 -Plano, TX 75074 CONTACT: Mike Worley 214-299-4300 Mob. 214-914-7854 ROOFD,IG CONTRACTOR: Pinkston Hollar 2887 A W. Pioneer Pkwy. - Arlington, TX ROOFING FOREMAN: Scott Lockwood Mob. 817-401-0809 MANLrFACTORER: Tamko System - Type III Asphalt- 4 ply with aggregate ballast Technical Information WEATHER CONDITIONS: Sunny AMBIENT TF_~VIPERATURES: 83 to 106 FOREC~ST FOR NEXT DAY: Same SIZE OF CREW: 27 ThME: 7 to 4 pm ROOFING MATERIALS RECEIVED? No LABELS ATTACHED? Yes MATERIALS STORED AS REQUIRED? Yes MATERIALS REJECTED? No SPECIFIED TEMPERATURES: (Asphalt) Kettle: 500 + 25 degrees F. EVT (Application): 450 +25 degrees F. Kettle: 12:00 pm- 500 EVT: 12:30 pm-465 DECK INSPECTED? Yes CRICKETS INSTALLED? No Location: NA AREA OF ROOF APPLICATION: G-P/13-17 Number ofSQ's (SF X 100) placed this date: 240 SQ Was placement per specifications: Yes OPERATIONS INSPECFED: Installation of 1.6" Iso insulation was mechanically attached to the deck with 2 V4'fasteners. Fourteen (14) in the corners, twelve (12) at the perimeter (eight feet into the field of the roof) and eight fasteners per 4' X 8' insulation board. Application of the V2" fesco insulation was as required. Staggered over the Iso seams and adhered in a solid mopping of hot asphalt. Cant strips were applied at the perimeter and around curbs, set in hot asphalt. Four (4) plies of Tamko fiberglass felts were applied in a lapping fashion., in a solid mopping of hot asphalt. Flashing detail was performed on the air conditioning penetrations. Mark roof for corrections, fishmouths and dry laps. ~*NOTE: The base flashing at location B-P/17 was not fully adhered at the seam laps. The roofing foreman was advised of the problem, as was the site superintendent, Mike Worley. The roofers will have to peel back the seam laps and re-mop and adhere these areas. Technician: Carlos Williams Time: 12 to 4pm