Gateway BP(1.2)-CS 960419The City With A Beautiful Future
P.O. Box 478
Coppell, Texas 75019
214-462-0022
April 19, 1996
Scott McCrary
Gromatzky Dupree & Associates
2626 Cole Avenue, Suite 100
LB Box 48
Dallas, Texas 75204
RE: Gateway Business Park, Replat of Block 1 (Fritz)
Development Fee Assessment
Dear Mr. McCrary:
Enclosed is a copy of the City of Coppell Development Fee Assessment list, along with a copy of
the Development Fee calculations for Gateway Business Park Replat of Block 1 (Fritz).
Please make payment to the City of Coppell in the amount of $83,823.14 and forward it to Jennifer
Armstrong, Finance Director, along with a copy of the Fee Assessment list. A copy of the
Engineer's estimate or contract for this project will need to be provided to our department so the
construction inspection fee can be verified
Providing a copy of your paid receipt to our office will help us to verify payment of the required
fees and insure a successful beginning of this project. We look forward to working with 3/ou on this
project. If you have any questions, please do not hesitate to contact me.
Sincerely,
Kenneth M. Griffin, P.E.
Assistant City Manager/City Engineer
cc:
Jennifer Armstrong, Finance Director
Doug Stevens, Engineering Technician
Ted Dutt, Interim Utilities Superintendent
Greg Jones, Chief Building Official
Per Birdsall, Street Division
Rick Wieland, Parks Development Coordinator
CITY OF COPPELL
DEVELOPMENT FEES
Date:
Project:
April 19, 1996
Fritz (Gateway)
TOTAL AMOUNT DUE
FEES DUE PRIOR TO
COUNCIL
APPROVAL
Water Impact Fee $19,125.00 $19,125.00
(100% due prior to Council Approval)
Water Tap Inspection Fee 350.00 -0-
(100% due at Issuance of Water Meter)
Wastewater Impact Fee 10,800.00 10,800.00
(100% due prior to Council Approval)
Sewer Tap Inspection Fee 200.00 -0-
(100% due at Issuance of Building Permi0
Utility Final Inspection Fee 50.00 -0-
(100% due at Issuance of Building Permit)
Water Meter Fee (Domestic) 1,637.94 -0-
(100% due at Issuance of Water Meter)
Water Meter Deposit (Non-residemial) 150.00 -0-
(100% due at Issuance of Water Meters)
Water Meter Fee (Irrigation & Fire) 9,190.98 -0-
(100% due at Issuance of Water Meters)
Irrigation Meter Deposit 70.00 -0-
(100% due at Issuance of Water Meters)
Street Sign Fee -0- -0-
(100% due prior to Acceptance of Project)
Street Light Fee * information not -O-
(100% due prior to Acceptance of Project) available
Park Fee -0- -0-
Street Escrow 53,898.14 53,898.14
(100% due prior to Council Approval)
Construction Inspection Fee need submittal of -0-
(2% of Project Cost due prior to Preconstr. Mtg.) contracts
TOTAL $ 95,472.06
TOTAL AMOUNT DUE PRIOR TO COUNCIL APPROVAL $ 83,823.14
* This fee cannot be assessed until after TU Electric submits the lighting plan for the proposed project. Once the plan
is submitted, $292.60 per light will be assessed.
COPPRnn ENGINEERING
HE~ORANDUM
DATE
TO:
FROM
RE:
April 12, 1996
Mike Martin, Assistant City Engineer
Ted Dutt, Interim Utilities Superintendent
Development Fees for Fritz (Gateway) REVISED
The following fees should be assessed and collected on the above
referenced project.
Water Impact Fee:
2
3
- (!} 2" (1~ 3" Domestic Meter/s
- 2" Irrigation Meter/s =
- (2; 8" {1; 10" Fireline Meter/s
Total
= 24 ESU's
~6 ESU's
= 2.5 ESU's
42.5 ESU'S @ $450.00 ea = $19.I25.00
100% due prior to Council approval of the final plat.
Wastewater Impact
2 - (1; 2" (1} 3" Domestic Meter/s = 24 ESU's
Total 24 ESU's @ $450.00 ea = $10,800.00
100% due prior to Council approval of the final plat.
Water Tap Inspe~ion Fee
7 Connections @ $50.~0 each = $350.00
100% due prior to issuance of building permit for residential. (Or in
the case of multi-family, commercial, retail, industrial, fee is due
prior to issuance of meter).
Sewer Tap Inspection Fee
4 Connections @ $50.00 each ~ $. 200.00
100% due prior to issuance of building permit. (Residential only)
(RE-INSPECTIONFOR WATER OR WAST~WATER $30.00)
Development Fees
Page 2
Utility Final Inspection Fee (Ail Development)
1 lots @ $ 5O.OO/lot = $50.00
100% due prior to issuance of building permit.
Water Weter Fee (Domestic)
1 - 3"
1 - 2"
Domestic Meters ~ $~ · 050.00 = $1,050.00
Domestic Meters ~ S195.98 = $587.94
Total $ 1o637.94
100% due prior to issuance of building permit for residential only.
Ail other development fees are due prior to issuance of meter/s.
Water Meter Fee
2 - 2"
~ - 8"
1 - 10"
(Irrigation/Fireline)
Irrigation Meter/s ~ $195.98 ea = $ 391.96
Fireline Meter/s @ $ 2,580.90ea = $5,161.80
Fireline Meters/s @ $3,6~7.20ea = $3.637.20
Total $9,190.98
100% due prior to issuance of water meter/s.
Water Meter Deposit (Multi-Family or Non-Residential)
5 Meters ~ $30.00 ea = $450.00
100% due prior to issuance of water meters.
Irrigation Meter Deposit
2 Meters ~ $35.00 ea = $70.00
100% due prior to issuance of water meters.
fritz2
ESCROV~ ROADWAY IMPACT FEE CA_ £ULATIONS
PROJECT:
DATE:
Gateway Business Park, Replat of Block 1 (Fritz)
4112/96
ROADWAY IMPACT FEE:
Service Area * 9
Ca.gory ** Industrial
Land Usc **
Suildin~ Size (ScI. Ft.)
Development Units **
Vehicle Miles per Development Unit **
Fee per Vehicle Mile
Roadway Impact Fee due = (Development Units) x
(Vehicle Miles per Development Unit) x (Fee per Vehicle Mile)
General Li~ht Indus~al
169,491
169.491
$3O0
$53,898.14
* (Figure 2- Roadway Impact Fee Smd./)
** (Table 3 - Roadway Impact Fee Study)