October 22, 1992
Mr. Alan D. Ratliff
City of CoppeR
P. O. Box 478
CoppeR, Texas 75019
Re: Copper Gateway Public Improvement District
Consmaction of Phase IB "Facilities"
Gentlemen:
On February 19, 1992, we submitted plans for Phase IB facilities to City Engineering for
initial review and plan checking. On October 6, 1992, we resubmitted the plans and other
construction contract documents for the referenced project to the City Engineering
Department, incorporating requested changes, for their review. Enclosed, for your review, is
a complete copy of the referenced documents. By copy of this letter, we will forward a copy
to your City Attorney, Lawrence W. Jackson, of Nichols, Jackson, Kirk & Dillard, for his
review and approval.
On October 19, 1992, we met with Halff Associates and City Engineer Ken Griffin to review
the Project and discuss any required revisions. Our schedule calls for:
october 26, 1992 Submit final consu'uction drawings and
(Monday) documents to the City of Copper
october 30, 1992 Advertise for bids in Citizen's Advocate
(Friday) (must submit ad to newspaper by previous deadline)
November 6, 1992 Re-advertise for bids
(Friday)
November 13, 1992 Receive bids
(Friday)
November 18, 1992 Finalize review and analysis of bids
(Wednesday)
November 24, 1992 City Council approval and award contract
(Tuesday)
November 25, 1992 Start construction
(Wednesday)
CATELLUS DEVELOPMENT CORPORATION
5429 LBJ FREEWA¥~ SUITE 600 · DALLAS. TEXAS 7524o-26o9 · TEL 214 98o-77o7 FAX 2I4 770-3272
Messrs. Ratliff and Trando
October 22, 1992
Page Two
If you have any questions, or if we need to make any adjustments to this schedule, please
advise. We look forward to a rapid and successful completion of this project.
T. Weldon Davis -
Vice President, Development