Loading...
WA9302-CS 961113 SHIMEK, JACOBS & FINKLEA, L.L.P. CONSULTING ENGINEERS 8333 Douglas Avenue, #820 Dallas, Texas 75225-5816 Fax (214) 361-0204 Phone (214) 361-7900 ROSS L. IACOBS, P.E. RONALD V. CONWAY, P.E. IOHN W. BIRKHOFF, P.E. so~ n. CANTER, P.E. November 13, 1996 GARY C. HENDRICKS, P.E. I. C. FINKLEA, P.E. Mr. Robert Barbarisi, Jr. Natgun Corporation Eleven Teal Road Wakefield, MA 01880-1292 Re: City of Coppell, Village Parkway Ground Storage Res. No. 2 Dear: Mr. Barbarisi At the request of Natgun, an informal walk through was conducted at the Village Parkway Ground Storage Reservoir No. 2 on September 24, 1996. The walk through was conducted in order to identify incomplete or defective work, prior to the final walk through on the ground storage tank. As of November 12, 1996, many of the defects noted have not been repaired. Following is a list of the outstanding work or repairs required: · Complete the instrumentation panel modifications as shown in the construction plans and noted in the project Specifications. The High and Low water level indicators and the four engraved annunciator cards were not furnished and installed. · Complete repairs to the sprinkler system in the areas noted on the system layout provided by the City. · Grout and seal the joints for the concrete driveway and curb repairs completed by Natgun. · Correct erosion problems on the slope near the west side of the existing driveway. · Seal the joint between the new concrete flume and the existing concrete channel. · Seal the void between the ground storage tank wall and the sidewalk. · Seal the void where the level transmitter conduit enters the dome of the ground storage tank. · Replant the fifty honeysuckle vines with planting beds as shown in the construction plans between the existing fence posts. · Reapply the temporary rye hydromulch to the areas where the previous seeding is washed away. · Furnish and install the Ground Storage Reservoir No. 2 plaque to the location that was indicated by the City. Mr. Robert Barbarisi, Jr. Natgun Corporation 11/13/96 Page No. 2 * Check the roof vent for possible weather related damage. , Seeding of Bermuda grass . .. A final walk through will be scheduled when the items above have been completed. We will call you later today to discuss the remaining work and your schedule for the completion of this project. Gary C. Hendricks, P.E. ~ Mr. Larry Davis