RE: Creekview Drive and Freeport Parkway Project ST 00-01
Construction Materials Testing
Dear Mr. Stettner:
The City of Coppell intends to construct the Creekview Drive and Freeport Parkway
Project. The project consists of approximately 2800 linear feet of four-lane undivided
roadway, the reconstruction of approximately 800 linear feet of an existing two-lane
road to a four-lane divided roadway, drainage improvements, sidewalks, and 3600
linear feet of 8- to 12-inch water line. It is anticipated that construction will begin in
October 2001. We are providing an estimate of the type and number of construction
materials tests required for the Project based on the construction plans and the City's
standards. Please submit a proposal for the construction materials testing.
Your consideration of this matter is appreciated and should you have any questions or
need any additional information, please contact me at 972-304-3679.
Sincerely,
Suzar(C~ Taylor
C.I.P.'~6ordinator
Attachments
255 PARKWAY ~ P.O BOX 478 ~ COPPELL TX 75019 1Ir TEL 972/462 0022 ~ FAX 972/304 3673
CREEKVIEW DRIVE & FREEPORT PARKWAY PROJECT (ST00-01)
CONSTRUCTION MATERIALS TESTING ESTIMATE
Site Preparation
Approximately 3000 C.Y. of fill material will be placed in two locations (15-foot depth
and 6-feet depth). (Assumed 1 FDT per 8" lift in each location)
1. Nuclear Density Test ..........: ........................... 31/each
2. Standard Proctor Test ....................................... 1/each
3. Atterberg-limit Test .......................................... 1/each
Mechanical Lime Stabilization
Approximately 19,000 S.Y. ( 3705 L.F.) of subgrade will be mechanically lime
stabilized. (Assumed 1 FDT and Gradation for each 300 L.F.)
1. Nuclear Density Test ..................................... 12/each
2. Standard Proctor Test ...................................... 3/each
3. Atterberg-limit Test ......................................... 3/each
4. Gradation ..................................................... 12/each
Concrete Testing
A total of 20,200 C.Y. will be placed. (Assumed 1 set of 4 cylinders each 150 C.Y.
plus another 25 9[ for hand-pours)
1. Concrete Compression Tests ....................... 670 cylinders
Utilities
Storm Sewer- (A total of 815 L.F. and assumed average depth of 5' and 1 FDT per
each 8" lift.)
Water Line - (A total of 2810 L.F. and assume an average depth of 3.5' and 1 FDT per
each 8" lift.) (A total of 850 L.F. and assumed an average depth of 6' and 1 FDT per
each 8" lift.)
1. Nuclear Density Test ..................................... 93/each
2. Standard Proctor Test ...................................... 5/each
3. Atterberg-limit Test ......................................... 5/each
HMAC
Approximately 1550 S.Y. of HMAC will be placed.
1. Asphalt Extraction Type "D" ........................... 1/each
2. Asphalt Extraction Type "B" . ........................... 1/each
Sidewalks
A total of 3530 L.F. of sidewalk will be constructed. (Assume 1 FDT for each 300
L.F.)
1. Nuclear Density Test .................................... 12/each