CASE: GATEWAY BUSINESS PARK~ LOT 2R,
BLOCK 2, REPLAT and SITE PLAN REVIEW
(ADVANCED GRAPHICS PRODUCTS, INC.)
P & Z HEARING DATE:
C.C. HEARING DATE:
LOCATION:
SIZE OF AREA:
November 18, 1999
December 14, 1999
Northwest comer of Gateway Boulevard and Exchange Circle.
Approximately 6 acres of property; 80,000 sf office/warehouse
CURRENT ZONING:
REQUEST:
APPLICANT:
LI (Light Industrial)
Replat and Site Plan review approval.
Owner:
Catellus Development Corp.
4545 Fuller Drive
Irving, TX 75038
(972) 719-6100
FAX: (972) 739-0095
Engineer:
HalffAssociates, Inc.
8616 Northwest Plaza Drive
Dallas, TX 75225
(214) 346-6200
FAX: (214) 739-0095
HISTORY:
The City Council approved the final plat of Gateway Business Park
on June 12, 1990, and a previous replat of Block 2 on April 9, 1996.
TRANSPORTATION:
Freeport Parkway is C4D/6 four-lane divided thoroughfare within a
95'-wide right-of-way. Gateway Boulevard is a C4U four-lane
undivided collector street within a 70'-wide right-of-way.
SURROUNDING LAND USE & ZONING:
North-
South -
East -
West -
Office/showroom/warehouse; "LI" Light Industrial
Office/warehouse; "LI" Light Industrial
vacant; "LI" Light Industrial
Office/showroom/warehouse; "LI" Light Industrial
Item # 5
COMPREHENSIVE PLAN:
The Comprehensive Plan shows the property as suitable for
light industrial/showroom use.
DISCUSSION:
Applicant is proposing an 80,000 square foot build-to-suit
industrial facility on this 6-acre tract, immediately east of
Haverty's. Approximately 80% of the interior space will be
devoted to warehouse space and the remaining 20% will be used as
office space.
This is a single story structure with 119 parking spaces and 6 track
bays located behind the building. The architectural elevations
indicate a painted tilt wall structure in white and gray tones with
green tinted glass, very comparable to the existing facilities in the
Gateway Business Park.
The submitted landscape plans indicate that approximately 36% of
the site will be landscaped. A number of existing Cedar Elms and
Crape Myrtles will be relocated on site to accommodate the
proposed construction. Staff is concerned that the truck court is
not adequately screened from Exchange Circle. Currently the plan
shows a Nellie R. Stevens Holly hedge with four staggered
Austrian Pines being planted to screen the truck court from
Exchange Circle. Staff requests the applicant consider a 3 foot
high berm with Austrian Pine planted on top of the berm, similar to
what is being proposed at the northwest corner of the site. During
the Development Review process, staff requested planting islands
in the proposed truck courts. During the course of discussion, the
applicant informed staff there were six truck bays and there were
landscaped areas east and west of the truck bays. After careful
review of both the site and landscape plans, staff is of the opinion
that the proposed staircases are separating 2 sets of 3 loading
spaces, thus creating 2 rows of loading spaces. The zoning
ordinance is specific that interior areas of the parking pavement
must contain planting islands. The islands must be at least 150
square feet of landscape area and contain a tree. Staff recommends
that the applicant incorporate the required landscaped area and a
tree to each of the staircases in the track court. Clarify on
drawings how many staircases are being proposed along the
northern elevation of the building. The site plan shows 3
staircases, while the landscape plan only shows 2.
The Red Yucca is not on the city's approved plant palette,
therefore, the applicant will have to substitute it with another plant
material. Also, a minor discrepancy was noted between the site
Item # 5
plan and landscape plan with regards to the total site area and that
will require correction.
RECOMM]ENDATION TO THE PLANNING AND ZONING COMMISSION:
Staff recommends approval of the site plan and replat subject to the following conditions
being met:
1) Approval of a color board showing all exterior building materials.
2) A 150 square foot of landscape area with a tree being incorporated into the staircases
shown in the track court.
3) Rectify the discrepancy of the total site square footages, as well as the number of
staircases shown on the site plan and landscape plan.
4) Substitute the Red Yucca shown on the Landscape plan with a plant material listed on
the city's approved plant palette.
5) Additional fire lane needed on south side (adjacent to Gateway Blvd. and Exchange
Circle). (See Fire Departmem comments)
6) An executed Tree Removal Permit will be required prior to removing trees from the
site. (See Leisure Services comments)
7) Easements for TXU facilities; will be required on plat. (See TXU comments)
ALTERNATIVES:
ATTACHMENTS:
Relative to the Replat:
1) Recommend approval of the replat.
2) Recommend denial of the replat.
Relative to the Site Plan:
1) Recommend approval of the request
2) Recommend denial of the request
3) Modify the request
4) Take under advisement for additional information
1) Replat
2) Site Plan
3) Floor Plan
4) Exterior Elevations
5) Landscape Plan
6) Irrigation Plan
7) Departmental Comments
Item# 5
DE VEL OPMENT .R E VIE W COMMITTEE
FIRE PRE VENTION COMMENTS
ITEM: GATEWAY BUSINESS PARK, REPLAT
DRC DATE: OCTOBER 28, 1999
CONTACT: TRAVIS CRUMP, F, RE MARSHAL g~2.$04.3$O$
COMMENT STA TUS: [
Additional fire lane needed on south side (adjacent to Gateway & Exchange). NOTE:
There is a discrepancy between the plat and the site plans on this fire lane.
L~,~sur~ SE~WCF, S CO~~]]~ !! OC~ z ~ ~
Gateway Business Park, Site Plan Review . __
DRC DATE: October 28, 1999 and November 4, 1999
CONTACT: Brad Reid, Park Planning and Landscape Manager
COMMENT STATUS:
PRELfMINARY_.~
A tree survey is required for this development, or a notation on the plans that no
existing trees will be impacted by the development.
An executed Tree Removal Permit will be required prior to removing trees from the site.
Developer must notify the Parks Department at 972-304-3554 prior to performing any
excavation in a median or ROW. The developer must repair any disturbed utility to
the satisfaction of the Parks Department.
DRC1028b
0 TXU
TXU Electric & Gas
4200 North Belt Une
Irvinc~ TX 75038
Comments for the City of Coppell
Development Review Committee
October 28, 1999
Gateway Business Park, Replat and Site Plan Review of Lot 2R, Block 2
Replat Unacceptable
Easements for TXU facilities will be required on plat. Please contact Jeff Curry at 972-570-4126
concerning easements and load information.