REPORT OF BUILT-UP ROOFING OBSERVATION
Parkwest Commerce Center - Building 2
Enterprise Drive at Wrangler Drive
Coppell, Texas
REPORTED TO:
Myers & Crow Company
3811 Turtle Creek Boulevard, Suite 730
Dallas, Texas 75219
ATTN: Mr. Richard Crow
McFadden & Miller, Inc.
JHEC Roofing, Inc.
~i~l Roof Skylights
REPORT NO. 63
REPORT DATE: 04-21-99
REG PROJECT NO. 4770
DATE OBSERVED: 03-19-99
TECHNICIAN: L. Johnson
PAGE: I of 1
~~] Partly Cloudy
I~ 48"'/49°
!:i !I] The metal work surrounding the skylights: Not completed.
Base flashing at various skylights are loose; rainwater getting
behind the flashing. Superintendent verified.
Roofing Materials As Specified: X Roof Sketch Attached: X
Labels Attached: X Debris Removed from Roof Surface: X
Material Sheet Attached: X Crickets Installed: N/A
Materials Stored as Required: X Deck Inspected: N/A
Non Conforming Materials Noted: X Photograph's taken this Date: X
Pull Test and/or Adhesion Test Performed: X Attachments: X
JAsphalt Kettle Temperature:I N/A +/- 25 F IApplication (EVT): N/A +/- 25 F J
Asphalt / Pitch Kettle Temperature: I Time Temp. Application (EVT): Time Temp.
I N/A N/A N/A N/A
Distribution: (4) Myers & Crow Company/
Mr. Richard Crow
(1) Pritchard Associates/
Mr. Jim Pritchard
(1) O'Brien & Associates/
Mr. Mick Granlund
(1) Technistructures/Mr. Keith Leslie
(1) McFadden & Miller/
Mr. Jon Jacobsen
Submitted by:
REED ENGINEERING GROUP, INC.
Original Signed By
Keith Atkins
MS/cav