Gateway BP(2.4)-CS 990420COPPELL, TEXAS 75019
Pat Acker, P.E.
HalffAssociates
8616 Northwest Plaza Drive
Dallas, Texas 75225
RE: Gateway Business Park No. 2, Lot 2 Bloek,~
Fee Assessment Letter
Dear Mr. Acker
Enclosed is a copy of the City of Coppell Development Fee Assessment
a copy of the Development Fee calculations for the referenced developme~
Please make payment to the City of Coppell in the amount of $50,130.59
the Finance Department along with a copy of the Fee Assessment table. ~[
portion of the assessed fees that need to be paid prior to Council approval.
the attached table for additional fees. Also provide a copy of the Engine~
contract to our office so the construction inspection fee can be verified.
Providing a copy of your paid receipt to the Engineering Department
verify the payment of required fees and insure a successful beginning of!
look forward to working with you on this project. If you have any qt
contact me.
Sincerely,
Michael A. Martin, P.E.
Assistant City Engineer
CC:
Jennifer Armstrong, Finance Director
Doug Stevens, Engineering Technician
Glenn Hollowell, Assistant Director of Public Works
Greg Jones, Chief Building Official
Gary Sims, Director of Leisure Services
P.O. Box 478
Coppell, Texas 75019
972-462-0022
April20,1999
ble, along with
rt.
and forward to
his amount is a
Please refer to
· 's estimate or
will help us to
his project. We
testions, please
DEVELOPMENT FEE TABLE
Project: Gateway Business Park No. II, Lot 2 Block A
Date: 4/20/99
TOTAL AMOUNT DUE
FEES DUE PRIOR TO
COUNCIL
APPROVAL
Water Impact Fee $11,925.00 $11,925.00
(100% due prior to Council Approval)
Water Tap Inspection Fee $200.00
(100% due at Issuance of Water Meter)
Water Meter Fee (Domestic) $1,098.83
(100 % due at Issuance of Water Meter)
Water Meter Fee (Irrigation/Fireline) $6,626.45
(100% due at Issuance of Water Meter)
Water Meter Deposit (Domestic) $35.00
(100% due at Issuance of Water Meter)
Irrigation/Fireline Meter Deposit $90.00
(100% due at Issuance of Water Meter)
Wastewater Impact Fee $7,200.00 $7,200.00
(100% due prior to Council Approval)
Wastewater Tap Inspection Fee $50.00
(100% due at Issuance of Building Permit)
Utility Final Inspection Fee $50.00
(100% due at Issuance of Building Permit)
Park Fee $0.00 $0.00
(100% due prior to Council Approval)
Roadway Impact Fee $31,005.59 $31,005.59
(100% due prior to Council Approval)
Street Light Fee Information not Ava lable
(100% due prior to Acceptance of Project II
Street Sign Fee Information not Ava ]able
(100% due prior to Acceptance of Project I]
Construction Inspection Fee Information not Ava ~able
II
FOTAL $58,280.87
TOTAL AMOUNT DUE PRIOR TO COUNCIL APPROVAL $50,130.59
DEVELOPMENT FEE WORKSHEET
PROJECT: Gateway Business Park No. 11, Lot 2 Block A
DATE: 4/20/99
Water Impact Fee:
Domestic Meter(s):
Irrigation Meter(s):
Fireline Meter(s):
I - 3 inch = 16 ES
1 - 2 inch = 8 ES
0 = 0 ES
2 - 8 inch = 2.5 ES
Total #: 26.5 ESU's @ $450.00 ea.
(100% due pdor to Council approval of the final plat)
Water Tap Inspection Fee:
Total #: 4 Connections @ $50.00 ea.
(Single family due prior to issuance of building permit)
(All other developments due prior to issuance of meter)
Domestic Water Meter Fee:
Total #: 1 Domestic Meter(s) @ $1,098.83
(Single family due prior to issuance of building permit)
(All other developments due prior to issuance of meter)
Irrigatio~/Fireline Water Meter Fee:
Total #: 1 Irrigation Meter(s) @
Total #: 0 Additional Irrigation Meter(s) @
Total #: 2 Fireline Meter(s) @
(100% due prior to issuance of water meters)
$192.05
$0.00
$3,217.20
Domestic Water Meter Deposit Fee:
Total #: 1 Meter(s) @ $35.00 ea.
(100% due prior to issuance of water meters)
IrrigationfFire Meter Deposit Fee:
Total #: 3 Meter(s) @ $30.00 ea.
(100% due prior to issuance of water meters)
Wastewater Impact Fee:
Total Domestic Meters ESU's:
16
@ $450.00 ea.
Wastewater Tap Inspection Fee:
Total #: I Connections @ $50.00 ea.
(100% due prior to issuance of building permit)
Utility Final Inspection Fee (Ail developments):
Total #: I Lots @ $50.00 ea.
(100% due prior to issuance of building permit)
Page 1
U's
U'S
U's
U'S
$11,925.00
$200.00
$1,098.83
$192.05
$0.00
$6,434.40
$35.00
$90.00
$7,2O0.O0
$50.00
$50.00
DEVELOPMENT FEE WORKSHEET
Park Fee (For Residential Developments Only): * Preliminary plat approved:
0
0
Single-family @ $0.00 per lot
Multi-family @ $0.00 per unit
(50% paid pdor to Council approval of final plat)
(50% paid at issuance of building permit)
Roadway Impact Fee:
(See attached fee calculations)
Street Lighting Fees:
Assessed for lighting in the City's right-of-way.
This fee cannot be assessed until after T.U. Electric submits
the lighting plan for the proposed development.
Once the plans are submitted, $292.60 per light will be assessed.
(100% due prior to final acceptance of development)
Street Sign Fees:
Assessed for signage in the City's right-of-way.
(See attached fee calculations if applicable)
Construction Inspection Fees:
A copy of the development contract must be submitted for assessment.
The contracts should indicate the cost to construct the improvements
that are inspected by the Engineering Department.
(2% of development cost required for private improvements)
(4% of development cost required for public improvements)
Page 2
$0.00
$o.o0
$31,005.59
Information not Available
Information not Available
Information not Available
ROADWAY IMPACT FEE CALCULATIONS
PROJECT:
DATE:
Gateway Business Park No. II, Lot 2 Block A
4/20/99
ROADWAY IMPACT FEE:
Service Area *
10
Category ** Office
Land Use ** General Office 15ldo.
Building Area Of) 103,611
Development Units ** 103.61
Vehicle Miles per Development Unit ** 3.99
Fee per Vehicle Mile ***
Roadway Impact Fee due = (Development Units) x
(Vehicle Miles per Development Unit) x (Fee per Vehicle Mile) --
* (Figure 2 - Roadway
** (Table 3 - Roadway
*** (Schedule 2, Page 3 - Roadway
Percent of Credit Toward Roadway Impact Fees
Total Credit
$124,022.37 i
Impact Fee Study)
Impact Fee Study)
Impact Fee Study)
75%
$93,016.78