Lakeside V2-CS 960723 COPPELL ENGINEERING
STREET DIVISION
MEMORANDUM
D~TE: July 23, 1996
TO: Larry Davis, Construction Inspector
FROM: Brent Adams, Street Division
RE: Walk thru for Krogers on Sandy Lake Rd.
A walk thru on the above referenced project was conducted on July
23, 1996 and the items below were found to be deficient.
I. MacArthur North Driveway
A. The curb on the northside of MacArthur's north
driveway at Pavers ADA needs to be repaired.
B. South side at the curb return the curb
spalled - also seal return.
C. Rout and seal cracks from both paver bands.
II. Right Turn Lane on the Southern Most Drive on MacArthur
A. Seal all curb saw cuts
B. Rout and seal cracks on the north and south ends of
the paver band.
C. Rout and seal crack on the center line of the drive
D. Seal all saw joints on the project
E. Repair all loose and/or damaged white buttons. Also
replace any missing white buttons.
Northbound Nac~thu~, LeEr Turn Lane
A. Rout and seal at new concrete to exisiting concrete
and curbs.
B. Rout and seal random cracks south of the manhole for
24" cross town and randum cracks off of the cut out
for the manhole.
IV. Sandy Lake East Driveway
A. Place safe hit posts on each side marking culvert or
head wall.
B. Rout and seal random crack east of the center line
pavers.
C. Rout and seal between asphalt and concrete along
Sandy Lake.
V. Sandy Lake West Driveway
A. Finish radius on the west end of the driveway.
B. Rout and seal between the asphalt and the concrete
along Sandy Lake.
C. Will pavement markings be placed on this drive?
Please ensure that these items get taken care of and if you have
any questions, please give me a call.
BA/cg
COPPELL EN~INEERI~
UTIL~T~E~ D~V~ON
~E~OI~,NDU~
DATE:
TO:
FROM:
RE:
JUly 23, 1996
Larry Davis, Construction Inspector
Larry Smith, Utilities Department
Walk thru for Krogers on SandyLake Rd.
A walk thru on the above referenced project was conducted on July
23, 1996 and the items below were found to be deficient.
2.
3.
4.
Put Chimney Seal in Manhole on SandyLake side.
Put Locking Hasp on vault.
Clean out meter boxes (meter & double are o.k.)
Put stack over meter cut off on MacArthur.
Please ensure that these items get taken care of and if you have
any questions, please give me a call.