Latter-day-CS 930617 (2) CITY OF COPPELL
PLANNING DEPARTMENT
STAFF REPORT
CASE #: S-1066
(The Church of Jesus Christ of Latter Day Saints Additk
P & Z HEARING DATE: June 17, 1993
C. C. HEARING DATE: July 13, 1993
LOCATION:
Fronting on the west side of MacArthur Boulevard,
Boulevard.
SIZE OF AREA: 3.527 Acres.
REQUEST:
Special use request for a church.
APPLICANT:
The Church of Jesus Christ
of Latter Day Saints
61 East N. Temple Street
Salt Lake City, Utah 84150
John R. Horton
P.O. Box 1537
Ft. Worth, Tex:
(817) 534-0222
HISTORY:
There has been no recent zoning history on this
originally heard on May 20, and held under advise
attempt to resolve traffic and other issues.
TRANSPORTATION:
MacArthur Boulevard is an improved P6D major tl
divided street contained within 110 feet of right-of-
SURROUNDING LAND USE & ZONING:
North - single-family residential - SF-0
South - single-family residential - SF-9
East - developing single-family residential - SF-~
West - single-family residential - SF-0
ITEM 6
,n)
southeast of Samuel
Architect
:act. This case was
aent until June 17 to
toroughfare, six-lane
~ay.
COMPREHENSIVE PLAN:
ANALYSIS:
ALTERNATIVES:
ATTACHMENTS:
s 1066. stf
The Comprehensive Plan shows low density single-fa
this parcel.
Because churches are identified as being compatibl
land use, this proposal meets the objective of our (
A close look at the site plan reflects the appropriate b
adequate yard dimensions, and landscaping which
criteria of the Streetscape Plan.
Our major development concern with this request rel
circulation, and patterns of traffic generation.
recommended that this church work with the CoppeI
District - the land owner adjacent on the west - ~
access from this site to Samuel Boulevard, probably 1:
alley. However, we have recently learned that CISD
across their school site. We also have concern
MacArthur Boulevard access is to be provided, the
naily development on
e with single-family
:omprehensive Plan.
rick screening walls,
appears to meet the
ites to traffic access,
We had strongly
· Independent School
:o provide vehicular
arallel to the existing
will not allow access
relative to where
~otential need for a
deceleration lane, and concems about alignments ~vith existing median
openings. Because of these concerns, a traffi9 study which will
satisfactorily address these issues was recommended and eventually
provided. ~
Other issues regarding drainage easements, fire hydrant requirements,
water and sanitary sewer issues will be addressed atlsubdivision platting.
Suffice it to say here that these concerns must be satisfactorily addressed
at platting.
If we receive satisfactory answers to our traffic-relal ed concerns outlined
above, and the site plan, landscaping, screening provision, circulation, and
aesthetic concerns are satisfactorily addressed, ap ~roval would be in
order.
1) Approve the zoning request
2) Deny the zoning request
3) Modify the zoning request
1) SUP Site Plan
2) Rendering