ST9302-CS010217FAX ('214) 352-3201 TELEPHONE (214) 358-6581
ED BELL CONSTRUCTION COMPANY
POST OFFICE BOX 540787 10605 HARRY HINES
DALLAS, TEXAS 75354-0787 DALLAS, TEXAS 75220
February 17, 2001
Mr. Kenneth M. Griffin, P.E.
Director of Engineering and Public Works
City of Coppell
255 Parkway Blvd.
Coppell, Texas 75019-4409
Re: Sandy Lake Road Reconstruction
Coppell Project #: ST 93-02
Kimley-Horn Project #: 06940600
DWU Project #: 98-311F
Dear Mr. Griffin:
Enclosed for your review is our project schedule for the remainder of the project. This schedule
reflects completion of the DWU lowerings prior to any work to progress the concrete pavement
in the MacArthur intersection. As a result, the project completion date has slipped to January
2002. The critical path of the project is now focused upon the four quadrants of the MacArthur
intersection. EBCC will explore construction methods that will accelerate this work.
Our September 11, 2000 schedule indicated our desire to start the intersection work in November
2000 and complete the SE quadrant prior to the DWU water line lowering in the MacArthur
intersection. Numerous conflicts at the MacArthur intersection have prevented any work in that
intersection and have resulted in significant delays that have affected the completion date of this
project.
If you have any questions regarding this schedule, don't hesitate to contact our office.
S~erely, h
l~d ]ilel~ Constr~dlqion Company
R~.~We~,
Project Manager
xc: Michael G. DeMotte, Kimley-Horn and Associates, Inc., 801 Cherry Street, Suite 1 ! 00
Fort Worth, Texas 76102-6803
AN EQUAL OPPORTUNITY EMPLOYER