REINFORCING STEEL PLACEMENT
Report Date January 15, 1996 Test Date: December 29, 1995
client City of Coppell General Report No.: 6
Project 6.0 MG Water Storage Tank Project No.: 95-196
Identification Field Inspection of Reinforcing Steel
Method of Test Visual Inspection
Results
On December 29, 1995 a representative of GEE Consultants, Inc. was present at the above
referenced project to perform reinforcing steel inspection:
Wall panels WE-I, WC-1, WB-1
Dome Panels 2B-l, 2A-l, 1A-l, 4A-l, 5A-l, 6A-l, 3A-l, 3B-l, 4B-l, 5B-l, 6B-l,
3C-1, 6C-1, 4C-1, 5C-1, 6D-l, 5D-l, 6F-l, 6E-l, 5E-l, 4D-1
The following discrepancies were noted and called to the attention of Bob, a representative of Natgun.
Weld tabs out of place in several locations.
The above discrepancies were corrected as noted. f ~
cc: Mr. Larry Davis - City of Coppell
Mr. Bob Barbarisi, Jr. - Natgun Corporation
Mr. Gary Hendricks - Shimek, Jacobs and Finklea