ST9302-CS010202 (2)FAX (214) 352-3201 TELEPHONE (214) 358-6581
ED BELL CONSTRUCTION COMPANY
POST OFFICE BOX 540787 10605 HARRY HINES
DALLAS, TEXAS 75354-0787 DALLAS, TEXAS 75220
February 2, 2001
Mr. Kenneth M. Griffin, P.E.
Director of Engineering and Public Works
City of Coppell
255 Parkway Blvd.
Coppell, Texas 75019-4409
Re: Sandy Lake Road Reconstruction
Coppell Project #: ST 93-02
Kimley-Horn Project #: 06940600
DWU Project #: 98-311F
Dear Mr. Griffin:
Enclosed for your review is our project schedule for the DWU lowerings east of Moore Road.
As discussed at the January 30, 2001 meeting regarding the DWU lowerings, this schedule
reflects closure of the MacArthur intersection from 9 p.m. on February 9, 2001 to 5:30 a.m. on
February 12, 2001 to complete the lowering in that intersection. Our utility subcontractor
understands that, regardless of the status of the water line lowering in the intersection, the
intersection must be open to traffic by 5:30 a.m. on February 12, 2001.
If you have any questions .regarding this schedule, don't hesitate to contact our office.
Sincerely,
E~~o~t~ Company
Robert D. Weber
Project Manager
xc: Michael G. DeMotte, Kimley-Horn and Associates, Inc., 801 Cherry Street, Suite 1100
Fort Worth, Texas 76102-6803
AN EQUAL OPPORTUNITY EMPLOYER