ST9302-CS 990211FAX (214) 352-3201 TELEPHONE (214) 358-6581
ED BELL CONSTRUCTION COMPANY
POST OFFICE BOX 540787 10605 HARRY HINES
DALLAS, TEXAS 75354-0787 DALLAS, TEXAS 75220
February 11, 1999
Mr. Kenneth M. Griffin, P.E.
Director of Engineering and Public Works
City of Coppell
255 Parkway Blvd.
Coppell, Texas 75019-4409
Re: Sandy Lake Road Reconstruction
Coppell Project #: ST 93-02
Kimley-Hom Project #: 06940600
DWU Project #: 98-311F
Dear Mr. Griffin:
Based upon our February 11, 1999 phone conversation and additional information from our
utility subcontractor, M-Co Construction, the prices for the two additional 16" gate valves to be
installed to isolate portions of the existing 16" water line have been revised. As directed, these
prices have been adjusted to include the cost to purchase and install the 16" valve. Our utility
subcontractor, M-Co Construction, has submitted the following prices to cut those valves into the
existing RCCP or DI water line:
1. Cost to cut-in 16" gate valve on RCCP line at Kimble Kourt $12,800.00
2. Cost to cut-in 16" gate valve on DI pipe near STA 54+00 $8,500.00
Please note that these prices do not include a vault or the bypass. Please add an additional eight
calendar days to the ~' ' ..
. pr, ,ject s duration for the two additional valves
If you have any questions regarding this issue, don't hesitate to contact our office.
Sincerely,
~~C:~pany
Robert D. Weber
Project Engineer
xc: Michael G. DeMotte, Kimley-Horn and Associates, Inc., 801 Cherry Street, Suite 1100
Fort Worth, Texas 76102-6803
AN EQUAL OPPORTUNITY EMPLOYER