January 2, 1999
Mr. Kenneth M. Griffin, P.E.
Director of Engineering and Public Works
City of Coppell
255 Parkway Blvd.
Coppell, Texas 75019-4409
Re: Sandy Lake Road Reconstruction
Coppell Project #: ST 93-02
Kimley-Hom Project #: 06940600
DWU Project #: 98-311F
Dear Mr. Griffin:
It is our understanding that the City of Coppell has requested that two additional 16" gate valves
be installed to isolate portions of the existing 16" water line. Our utility subcontractor, M-Co
Construction, has submitted the following prices to cut those valves into the existing RCCP or DI
water line:
1. Additional cost to cut-in 16" gate valve on RCCP line $4,300.00
2. Additional cost to cut-in 16" gate valve on ductile iron pipe $3,900.00
Please note that these prices are for extra work only and that the gate valve and vault would still
need to be paid utilizing pay item #94 - 16" M.J. Gate Valve and Vault. Please add an additional
eight calendar days to the project's duration for the two additional valves.
If you have any questions regarding this issue, don't hesitate to contact om office.
~i~cerely,
ell Const tion Company
Robert D. Weber
Project Engineer