WA9302-LR 951106 (4)'EOTECHNICAL
E GEE Consultants, Inc.
EiNViRONMENTAL
2540 Glenda Lane · Suite 108 · Dallas, Texas 75229 · (214) 620-9791 · Fax (214) 620-9794
GENERAL REPORT
Report Date November 6, 1995 Test Date: October 31, 1995
client City of Coppell General Report No.: 4
Project 6.0 MG Water Storage Tank Project No.: 95-0220
Identification Pier Inspection
Method of Test Visual Observation
Results
Scheduled time: 7:30 am
Type of service scheduled: Pier Inspection
Time left lab: 7:00 am
Time arrived at job: 7:25 am
Time left job: 11:30 am
Time returned lab:, 11:45 am
Total Charged Time: 4.75 hrs.
Reason: Contractor set 5 pipes for casing, but they did not pour concrete due to wet conditions in the field.
Concrete truck can not move on pad so they decided to cancel.
Technician: P.Chen
cc: Mr. Larry Davis - City of Coppell
Mr. Bob Barbarisi, Jr. - Natgun Corporation
Mr. Gary Hendricks - Shimek, Jacobs and Finklea